Braes of Doune Wind Farm is a 72 MW onshore wind farm in Scotland, operated by Greencoat Capital. The UK government lists it as operational in its register of power stations (DUKES table 5.11, May 2025).

  • Onshore
  • Scotland
Project stageOperating
  1. PlanningOct 2002 (completed)
  2. ConsentedOct 2004 (completed)
  3. ConstructionMay 2006 (completed)
  4. OperatingSep 2006 (current stage)
  5. Closed (not yet reached)

Planning dates from the Renewable Energy Planning Database; operating status from DUKES table 5.11.

Key facts

Installed capacity
72 MW
Status
Operational
Technology
Wind Β· Onshore
Operator
Greencoat Capital
Region
Scotland
Country
Scotland
Grid connection (DUKES)
HV
Combined heat & power
No
Coordinates
56.2698, -4.0589

Location

Map position from the published coordinates. For small sites this can be an approximate point rather than the exact boundary. Map Β© OpenStreetMap contributors.

How Braes of Doune Wind Farm compares

72nd of 488largest wind farms in the UK register
33rd of 199in Scotland
0.24%of listed UK wind farms capacity
β‰ˆ 164 GWhillustrative output a year

At a typical UK load factor for this technology (about 26% of the maximum possible output), a 72 MW station would generate roughly 164 GWh of electricity in a year, similar to the annual use of about 60,740 homes at 2,700 kWh each. This is an illustrative estimate, not the station's metered output: real generation varies with weather, availability and grid constraints.

Wind farms turn the kinetic energy of the wind into electricity with turbines. Output varies with wind speed. Offshore sites usually see stronger, steadier winds than onshore sites and so generate more per MW of capacity.

All UK wind farms Wind farms in Scotland All run by Greencoat Capital

Planning history

From the government's Renewable Energy Planning Database (REPD), matched to this site by location, capacity and name.

Planning status
Operational
Site name in planning record
Braes O'Doune
Developer / operator
Greencoat UK Wind
Planning authority
Scottish Government (S36)
Planning reference
S/02/01320/NST
Application submitted
31 October 2002
Permission granted
5 October 2004
Construction started
1 May 2006
Began operating
1 September 2006
Capacity in planning record
72 MW
Address
Stirling, 2 km to the north of Braes of Doune, Stirling
REPD reference
3119

Source

Department for Energy Security and Net Zero (DESNZ), Digest of UK Energy Statistics (DUKES), table 5.11: power stations in the United Kingdom β€” operational at end of May 2025. Capacity is installed capacity as published, not current output. Status reflects the source date, not live operation.
View the original source
Last checked by Octary: 15 July 2026

Spotted an error? Tell us and we will check it against the source.