Eveley
Eveley is a 49.3 MW solar farm in South East England, operated by Greencoat Capital. The UK government lists it as operational in its register of power stations (DUKES table 5.11, May 2025).
- PV
- South East
- England
Key facts
- Installed capacity
- 49.3 MW
- Status
- Operational
- Technology
- Solar Β· PV
- Operator
- Greencoat Capital
- Region
- South East
- Country
- England
- Grid connection (DUKES)
- LV
- Combined heat & power
- No
- Postcode
- SO20 6SA
- Coordinates
- 51.0978, -1.5328
Location
Map position from the published coordinates. For small sites this can be an approximate point rather than the exact boundary. Map Β© OpenStreetMap contributors.
How Eveley compares
At a typical UK load factor for this technology (about 10% of the maximum possible output), a 49.3 MW station would generate roughly 43 GWh of electricity in a year, similar to the annual use of about 16,000 homes at 2,700 kWh each. This is an illustrative estimate, not the station's metered output: real generation varies with weather, availability and grid constraints.
Solar photovoltaic (PV) sites generate electricity from sunlight. Panels produce direct current, which inverters convert to alternating current for the grid. Output follows daylight and the seasons, so annual generation is a small fraction of the maximum possible.
All UK solar farms Solar farms in South East All run by Greencoat CapitalNearby generating sites
- Westover Β· 7.04 MW solar farm7.4 km
- Fullerton Β· 4.36 MW solar farm9.3 km
- Lains Farm Β· 4.54 MW solar farm12.5 km
- Warren Β· 4.99 MW solar farm13.0 km
- Hale Farm Solar Ltd Β· 12.2 MW solar farm14.1 km
- Shipton Bellinger Β· 5.43 MW solar farm14.2 km
- Owls Lodge Β· 10 MW solar farm14.7 km
- Parkhouse Β· 6.64 MW solar farm14.7 km
Also operated by Greencoat Capital
Greencoat Capital operates 195 sites in the register. Largest first:
Planning history
From the government's Renewable Energy Planning Database (REPD), matched to this site by location, capacity and name.
- Planning status
- Operational
- Site name in planning record
- Eveley Farm
- Developer / operator
- PS Renewables
- Planning authority
- Test Valley
- Planning reference
- 15/00094/FULLS
- Application submitted
- 16 February 2015
- Permission granted
- 27 July 2015
- Construction started
- 1 March 2016
- Began operating
- 17 March 2016
- Capacity in planning record
- 49 MW
- Address
- Land At Eveley Farm Stevens Drove Houghton Stockbridge, Hampshire, SO20 6SA
- REPD reference
- 5080
Source
Department for Energy Security and Net Zero (DESNZ), Digest of UK Energy Statistics (DUKES), table 5.11: power stations in the United Kingdom β operational at end of May 2025.
Capacity is installed capacity as published, not current output. Status reflects the source date, not live operation.
View the original source
Last checked by Octary: 15 July 2026
Spotted an error? Tell us and we will check it against the source.