πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content
WIND Β· OPERATIONAL

Burnfoot

Burnfoot is a 30.1 MW onshore wind farm in Scotland, operated by EDF Energy. The UK government lists it as operational in its register of power stations (DUKES table 5.11, May 2025).

  • Onshore
  • Scotland

Key facts

Installed capacity
30.1 MW
Status
Operational
Technology
Wind Β· Onshore
Operator
EDF Energy
Region
Scotland
Country
Scotland
Grid connection (DUKES)
LV
Combined heat & power
No
Postcode
FK14 7JZ
Coordinates
56.2091, -3.7728

Location

Map position from the published coordinates. For small sites this can be an approximate point rather than the exact boundary. Map Β© OpenStreetMap contributors.

How Burnfoot compares

158th of 488largest wind farms in the UK register
92nd of 199in Scotland
0.10%of listed UK wind farms capacity
β‰ˆ 69 GWhillustrative output a year

At a typical UK load factor for this technology (about 26% of the maximum possible output), a 30.1 MW station would generate roughly 69 GWh of electricity in a year, similar to the annual use of about 25,390 homes at 2,700 kWh each. This is an illustrative estimate, not the station's metered output: real generation varies with weather, availability and grid constraints.

Wind farms turn the kinetic energy of the wind into electricity with turbines. Output varies with wind speed. Offshore sites usually see stronger, steadier winds than onshore sites and so generate more per MW of capacity.

All UK wind farms Wind farms in Scotland All run by EDF Energy

Planning history

From the government's Renewable Energy Planning Database (REPD), matched to this site by location, capacity and name.

Planning status
Operational
Site name in planning record
Burnfoot Hill
Developer / operator
EDF Energies Nouvelles
Planning authority
Clackmannanshire
Planning reference
06/00121/FULL
Application submitted
20 March 2006
Permission granted
28 March 2007
Construction started
1 August 2010
Began operating
26 October 2010
Capacity in planning record
26 MW
Address
Burnfoot Hill, Clackmannanshire, Clackmannanshire
REPD reference
2902

Source

Department for Energy Security and Net Zero (DESNZ), Digest of UK Energy Statistics (DUKES), table 5.11: power stations in the United Kingdom β€” operational at end of May 2025. Capacity is installed capacity as published, not current output. Status reflects the source date, not live operation.
View the original source
Last checked by Octary: 15 July 2026