WIND Β· OPERATIONAL

Green Knowes

Green Knowes is a 27 MW onshore wind farm in Scotland, operated by Scottish Power. The UK government lists it as operational in its register of power stations (DUKES table 5.11, May 2025).

  • Onshore
  • Scotland
Project stageOperating
  1. PlanningAug 2004 (completed)
  2. ConsentedJun 2008 (completed)
  3. ConstructionJun 2008 (completed)
  4. OperatingSep 2008 (current stage)
  5. Closed (not yet reached)

Planning dates from the Renewable Energy Planning Database; operating status from DUKES table 5.11.

Key facts

Installed capacity
27 MW
Status
Operational
Technology
Wind Β· Onshore
Operator
Scottish Power
Region
Scotland
Country
Scotland
Grid connection (DUKES)
LV
Combined heat & power
No
Postcode
FK14 7JY
Coordinates
56.2492, -3.6663

Location

Map position from the published coordinates. For small sites this can be an approximate point rather than the exact boundary. Map Β© OpenStreetMap contributors.

How Green Knowes compares

183rd of 488largest wind farms in the UK register
113th of 199in Scotland
0.09%of listed UK wind farms capacity
β‰ˆ 61 GWhillustrative output a year

At a typical UK load factor for this technology (about 26% of the maximum possible output), a 27 MW station would generate roughly 61 GWh of electricity in a year, similar to the annual use of about 22,780 homes at 2,700 kWh each. This is an illustrative estimate, not the station's metered output: real generation varies with weather, availability and grid constraints.

Wind farms turn the kinetic energy of the wind into electricity with turbines. Output varies with wind speed. Offshore sites usually see stronger, steadier winds than onshore sites and so generate more per MW of capacity.

All UK wind farms Wind farms in Scotland All run by Scottish Power

Planning history

From the government's Renewable Energy Planning Database (REPD), matched to this site by location, capacity and name.

Planning status
Operational
Developer / operator
CRE Energy/ Scottish Power
Planning authority
Perth and Kinross
Planning reference
04/01651/FUL
Application submitted
4 August 2004
Permission granted
13 June 2008
Construction started
14 June 2008
Began operating
29 September 2008
Capacity in planning record
27 MW
Address
Land at Green Knowes, by Glendevon, Tayside
REPD reference
3487

Source

Department for Energy Security and Net Zero (DESNZ), Digest of UK Energy Statistics (DUKES), table 5.11: power stations in the United Kingdom β€” operational at end of May 2025. Capacity is installed capacity as published, not current output. Status reflects the source date, not live operation.
View the original source
Last checked by Octary: 15 July 2026