WIND Β· OPERATIONAL

Whitelee I

Whitelee I is a 322 MW onshore wind farm in Scotland, operated by Scottish Power. The UK government lists it as operational in its register of power stations (DUKES table 5.11, May 2025).

  • Onshore
  • Scotland

Key facts

Installed capacity
322 MW
Status
Operational
Technology
Wind Β· Onshore
Operator
Scottish Power
Region
Scotland
Country
Scotland
Grid connection (DUKES)
HV
Combined heat & power
No
Postcode
KA3 6EX
Coordinates
55.6812, -4.2791

Location

Map position from the published coordinates. For small sites this can be an approximate point rather than the exact boundary. Map Β© OpenStreetMap contributors.

How Whitelee I compares

23rd of 488largest wind farms in the UK register
7th of 199in Scotland
1.1%of listed UK wind farms capacity
β‰ˆ 733 GWhillustrative output a year

At a typical UK load factor for this technology (about 26% of the maximum possible output), a 322 MW station would generate roughly 733 GWh of electricity in a year, similar to the annual use of about 271,620 homes at 2,700 kWh each. This is an illustrative estimate, not the station's metered output: real generation varies with weather, availability and grid constraints.

Wind farms turn the kinetic energy of the wind into electricity with turbines. Output varies with wind speed. Offshore sites usually see stronger, steadier winds than onshore sites and so generate more per MW of capacity.

All UK wind farms Wind farms in Scotland All run by Scottish Power

Planning history

From the government's Renewable Energy Planning Database (REPD), matched to this site by location, capacity and name.

Planning status
Operational
Site name in planning record
Whitelee
Developer / operator
CRE Energy/ Scottish Power
Planning authority
Scottish Government (S36)
Planning reference
2002/0001/EB
Application submitted
23 January 2002
Permission granted
1 April 2006
Construction started
1 December 2006
Began operating
14 December 2007
Capacity in planning record
322 MW
Address
Eaglesham Moor, Whitelee Forest, Fenwick Moor, East Kilbride, South of Glasgow, Strathclyde
REPD reference
3489

Source

Department for Energy Security and Net Zero (DESNZ), Digest of UK Energy Statistics (DUKES), table 5.11: power stations in the United Kingdom β€” operational at end of May 2025. Capacity is installed capacity as published, not current output. Status reflects the source date, not live operation.
View the original source
Last checked by Octary: 15 July 2026

Spotted an error? Tell us and we will check it against the source.