Home β€Ί Grid infrastructure β€Ί Connection queue

NESO TEC REGISTER Β· GREAT BRITAIN

Battery storage projects in the connection queue on the SSEN Transmission (north Scotland) network

Every generator, battery and interconnector with an agreement to connect to the GB transmission network, from early scoping to built. Filter by technology, stage or network, and open a project for its connection details.

Projects shown141.3 GW in total
In planning91scoping or awaiting consent
Consented or building16closest to connecting
Built4connected and operating

Map

Loading projects…

Voltage400 kV275 kV132 kVHVDCNew HVAC

ProjectsPlanningConsentedConstructionBuiltMajor project with its own page

Projects

14 projects
ProjectCapacityStageConnection siteFrom
Blackhillock Battery
Battery storage Β· Blackhillock Flexpower Ltd
349 MWConsents Approved Blackhillock 400kV Substation
SSEN Transmission (north Scotland)
Oct 2028
Zenobe Blackhillock 300 MW
Battery storage Β· Zenobe Blackhillock Limited
300 MWConsents Approved Blackhillock 275kV Substation
SSEN Transmission (north Scotland)
Apr 2026
MeyGen Tidal
Battery storage Β· Meygrid Limited
237 MWConsents Approved Gills Bay GSP
SSEN Transmission (north Scotland)
Apr 2028
Rothienorman 50MW BESS
Battery storage Β· Rothienorman Flexpower Ltd
50 MWConsents Approved Rothienorman 400/33kV Substation
SSEN Transmission (north Scotland)
Jul 2027
Corshellach Battery Energy Storage System
Battery storage Β· Corshellach Energy Storage Limited
50 MWConsents Approved Berryburn 275/33kV GSP Substation
SSEN Transmission (north Scotland)
Oct 2028
Drum Farm Energy Storage Facility
Battery storage Β· Field Drum Farm Ltd
50 MWConsents Approved Keith 2 132/33kV GSP Substation
SSEN Transmission (north Scotland)
Oct 2026
Lovat Estate BESS
Battery storage Β· LG-B-50a Limited
50 MWConsents Approved Beauly 132/33 kV GSP Substation
SSEN Transmission (north Scotland)
May 2026
Meetlaw BESS
Battery storage Β· Carravindoon Limited
50 MWConsents Approved Fiddes GSP
SSEN Transmission (north Scotland)
Oct 2031
Overhill BESS
Battery storage Β· Pulse Clean Energy Spv Watt Limited
50 MWConsents Approved Rothienorman 2 400/33kV GSP
SSEN Transmission (north Scotland)
Oct 2024
Coupar Angus Battery
Battery storage Β· Coupar Limited
40 MWConsents Approved Coupar Angus 132/33kV GSP
SSEN Transmission (north Scotland)
Feb 2022
Keith Battery Storage
Battery storage Β· Field Keith Ltd
39 MWConsents Approved Keith 1 132/33kV GSP Substation
SSEN Transmission (north Scotland)
Oct 2026
Arbroath Battery Substation
Battery storage Β· Arbroath Limited
35 MWConsents Approved Arbroath GSP
SSEN Transmission (north Scotland)
Feb 2022
MeyGen Tidal
Battery storage Β· Meygrid Limited
28 MWConsents Approved Gills Bay GSP
SSEN Transmission (north Scotland)
Apr 2027
Tarland Battery Storage System
Battery storage Β· Tarland Limited
20 MWConsents Approved Tarland 132/33kV GSP Substation
SSEN Transmission (north Scotland)
Oct 2026

Sources: NESO Transmission Entry Capacity (TEC) register and interconnector register (downloaded 8 November 2026); NESO Clean Power 2030 network map (existing and planned circuits, substations and network projects); National Grid Electricity Transmission overhead line routes. Contains data from NESO, licensed under the NESO Open Data Licence, and National Grid open data. Projects are placed at their connection substation, not the generating site; projects at new, unnamed β€œconnection nodes” are listed but not mapped.