Grid infrastructure › Connection queue › Battery storage

BATTERY STORAGE · SHET

Keith Battery Storage

Keith Battery Storage is a 39 MW battery storage project consented, connecting to the SSEN Transmission (north Scotland) network at Keith 1 132/33kV GSP Substation, with capacity due from October 2026. The connection agreement is held by Field Keith Ltd.

Project stageConsented
  1. Planning (completed)
  2. Consented (current stage)
  3. Construction (not yet reached)
  4. OperatingFrom Oct 2026 (not yet reached)
  5. Closed (not yet reached)

Connection details

NESO project number
PRO-001742
Customer
Field Keith Ltd
Technology
Energy Storage System
Total capacity
39 MW
Change in this agreement
+39 MW
Capacity effective from
31 October 2026
Connection site
Keith 1 132/33kV GSP Substation
Transmission owner
SSEN Transmission (north Scotland)
Connection type
Embedded (connects through the local distribution network)
NESO project status
Consents Approved
Connections reform gate
Gate 2

Connection site

The marker shows the connection substation, not the project itself, with the transmission network around it.

Projects connecting near Keith · Grid map

Source: NESO Transmission Entry Capacity (TEC) register, downloaded 8 November 2026. Contains data from NESO, licensed under the NESO Open Data Licence. Report a problem