BATTERY STORAGE Β· SHETLovat Estate BESS
Lovat Estate BESS is a 50 MW battery storage project consented, connecting to the SSEN Transmission (north Scotland) network at Beauly 132/33 kV GSP Substation, with capacity due from May 2026. The connection agreement is held by LG-B-50a Limited.
Project stageConsented
- Planning (completed)
- Consented (current stage)
- Construction (not yet reached)
- OperatingFrom May 2026 (not yet reached)
- Closed (not yet reached)
Connection details
- NESO project number
- PRO-003062
- Customer
- LG-B-50a Limited
- Technology
- Energy Storage System
- Total capacity
- 50 MW
- Change in this agreement
- +50 MW
- Capacity effective from
- 31 May 2026
- Connection site
- Beauly 132/33 kV GSP Substation
- Transmission owner
- SSEN Transmission (north Scotland)
- Connection type
- Embedded (connects through the local distribution network)
- NESO project status
- Consents Approved
- Connections reform gate
- Gate 2
Connection site
The marker shows the connection substation, not the project itself, with the transmission network around it.
Source: NESO Transmission Entry Capacity (TEC) register, downloaded 8 November 2026. Contains data from NESO, licensed under the NESO Open Data Licence. Report a problem