πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

Grid infrastructure β€Ί Connection queue β€Ί Battery storage

BATTERY STORAGE Β· SHET

Meetlaw BESS

Meetlaw BESS is a 50 MW battery storage project consented, connecting to the SSEN Transmission (north Scotland) network at Fiddes GSP, with capacity due from October 2031. The connection agreement is held by Carravindoon Limited.

Project stageConsented
  1. Planning (completed)
  2. Consented (current stage)
  3. Construction (not yet reached)
  4. OperatingFrom Oct 2031 (not yet reached)
  5. Closed (not yet reached)

Connection details

NESO project number
PRO-001966
Customer
Carravindoon Limited
Technology
Energy Storage System
Total capacity
50 MW
Change in this agreement
+50 MW
Capacity effective from
31 October 2031
Connection site
Fiddes GSP
Transmission owner
SSEN Transmission (north Scotland)
Connection type
Embedded (connects through the local distribution network)
NESO project status
Consents Approved

Connection site

The marker shows the connection substation, not the project itself, with the transmission network around it.

Projects connecting near Fiddes GSP Β· Grid map

Other projects at Fiddes GSP

Source: NESO Transmission Entry Capacity (TEC) register, downloaded 8 November 2026. Contains data from NESO, licensed under the NESO Open Data Licence. Report a problem