Grid infrastructure βΊ Connection queue βΊ Battery storage
BATTERY STORAGE Β· SHETFiddes Battery Storage
Fiddes Battery Storage is a 30 MW battery storage project in planning, connecting to the SSEN Transmission (north Scotland) network at Fiddes GSP, with capacity due from October 2028. The connection agreement is held by Fiddes Battery Limited.
- Planning (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingFrom Oct 2028 (not yet reached)
- Closed (not yet reached)
Scoping and awaiting consents are both shown as planning. A connection agreement does not mean the project will be built: many queue projects never reach construction.
Connection details
- NESO project number
- PRO-001831
- Customer
- Fiddes Battery Limited
- Technology
- Energy Storage System
- Total capacity
- 30 MW
- Change in this agreement
- +30 MW
- Capacity effective from
- 31 October 2028
- Connection site
- Fiddes GSP
- Transmission owner
- SSEN Transmission (north Scotland)
- Connection type
- Embedded (connects through the local distribution network)
- NESO project status
- Scoping
Connection site
The marker shows the connection substation, not the project itself, with the transmission network around it.
Other projects at Fiddes GSP
Source: NESO Transmission Entry Capacity (TEC) register, downloaded 8 November 2026. Contains data from NESO, licensed under the NESO Open Data Licence. Report a problem