Projects shown1,590616.3 GW in total
In planning1,590scoping or awaiting consent
Consented or building265closest to connecting
Built400connected and operating

Map

Loading projects…

Voltage400 kV275 kV132 kVHVDCNew HVAC

ProjectsPlanningConsentedConstructionBuiltMajor project with its own page

Projects

1,590 projects · page 20 of 32
ProjectCapacityStageConnection siteFrom
TH Knaresborough
Battery storage · FRV Powertek Limited
200 MWScoping Leeds North Connection Node A 400kV Substation
National Grid (England & Wales)
Oct 2036
TH Maes Melin
Battery storage · FRV Powertek Limited
200 MWScoping South Wales West Connection Node A 400kV Substation
National Grid (England & Wales)
Oct 2037
TH Ninfield
Battery storage · FRV Powertek Limited
200 MWScoping Sussex and Romney Connection Node A 400kV Substation
National Grid (England & Wales)
Oct 2037
TH West Weybridge
Battery storage · FRV Powertek Limited
200 MWScoping London West Connection Node B 400kV Substation
National Grid (England & Wales)
Oct 2037
Thornton BESS
Battery storage · Rewe 9 Limited
200 MWScoping North Humber Connection Node C 400kV Substation
National Grid (England & Wales)
Oct 2035
Thurcroft Storage
Battery storage · Bsr Applications Limited
200 MWScoping Leeds South Connection Node B 132kV Substation
National Grid (England & Wales)
Oct 2039
Tolkien Solar Farm
Solar + storage · Tolkien Solar Farm Limited
200 MWScoping Tolkien Farm 132kV Substation
SSEN Transmission (north Scotland)
Oct 2033
Tyler Hill Ansty
Battery storage · FRV Tyler Hill BESS 1 Ltd
200 MWScoping Warwickshire Connection Node D 132kV Substation
National Grid (England & Wales)
Oct 2037
UK105-B Upland Arms
Solar + storage · Uruk BESS Limited
200 MWScoping Llandyfaelog 400/132kV Substation
National Grid (England & Wales)
Dec 2036
Walsoken Battery
Battery storage · Walsoken Limited
200 MWScoping North Anglia Connection Node D 132kV Substation
National Grid (England & Wales)
Oct 2034
Waltham Cross Farm
Solar + storage · Waltham Cross 2 Renewables Limited
200 MWScoping Waltham Cross 400kV Substation
National Grid (England & Wales)
Apr 2033
Warley Battery Energy Storage
Battery storage · London And Essex Energy Limited
200 MWScoping Warley 275kV Substation
National Grid (England & Wales)
Oct 2029
West Melton PV & BESS Station
Solar + storage · Ibv West Melton Solar Park Limited
200 MWScoping Leeds North Connection Node C 400kV Substation
National Grid (England & Wales)
Oct 2035
West Saval Battery Storage
Battery storage · West Saval Battery Storage Ltd
200 MWScoping West Saval Substation 132 kV
SSEN Transmission (north Scotland)
Oct 2030
Whitecraig BESS
Battery storage · Apatura Battery Ltd
200 MWScoping Dalkeith 400kV Substation
SP Transmission (south Scotland)
Jun 2031
WindyHill BESS2 Facility
Battery storage · Windyhill Grid 2 Ltd
200 MWScoping Windyhill 275/132kV
SP Transmission (south Scotland)
Jul 2025
Womblehill BESS Farm
Battery storage · RE Projects Development Limited
200 MWScoping Womblehill BESS Farm 132kV
SSEN Transmission (north Scotland)
Dec 2029
Woodcock Faulds Battery Storage
Battery storage · Woodcock Faulds Battery Storage Limited
200 MWScoping Gartclash Collector 275Kv Substation
SP Transmission (south Scotland)
Oct 2029
Yaxley BESS
Battery storage · Field Yaxley Ltd
200 MWScoping North Anglia Connection Node E 400kV Substation
National Grid (England & Wales)
Oct 2034
Yaxley Farm
Solar + storage · 548 UK Investment Holdings Limited
200 MWScoping Yaxley 400kV Substation
National Grid (England & Wales)
Oct 2032
Zenobe New Deer Battery Storage
Battery storage · Zenobe Energy Limited
200 MWScoping New Deer 400kV Substation
SSEN Transmission (north Scotland)
Oct 2029
Tyler Hill Iver
Battery storage · FRV Powertek Limited
200 MWAwaiting Consents London West Connection Node A 400kV Substation
National Grid (England & Wales)
Oct 2038
Manor Farm_Sidcup
Battery storage · Firstway Solar Ltd
200 MWScoping North Kent Connection Node C 132Kv Substation
National Grid (England & Wales)
Oct 2037
Mill Hey_Capenhurst BESS
Battery storage · Firstway Solar Ltd
200 MWScoping Capenhurst GSP
National Grid (England & Wales)
Oct 2037
Inveroykel Wind Farm
Onshore wind · Rwe Renewables UK Swindon Limited
191 MWScoping Inveroykel Wind Farm 132kV
SSEN Transmission (north Scotland)
Oct 2031
Drax
Solar + storage · Enso Green Holdings D Limited
190 MWAwaiting Consents Drax 132kV Substation
National Grid (England & Wales)
Oct 2029
Llanwern Phase 2
Solar · Future Energy Llanwern Limited
190 MWAwaiting Consents Whitson 275kV Substation
National Grid (England & Wales)
Oct 2028
Garreg Fawr Energy Park
Onshore wind · Garreg Fawr Energy Park Limited
190 MWScoping Pont Abraham GSP
National Grid (England & Wales)
Oct 2026
Tarenni
Onshore wind · Tarenni Energy Park Limited
188 MWScoping Rhigos 400kV Substation
National Grid (England & Wales)
Dec 2030
Clune Wind Farm
Wind + storage · Renewable Energy Systems Limited
187 MWScoping Clune 132/33 kV Substation
SSEN Transmission (north Scotland)
Apr 2030
M74 West Wind Farm
Solar + storage · Renewco Power Limited
180 MWScoping M74 West Wind Farm 132kV
SP Transmission (south Scotland)
Oct 2029
NEL Nicholson
Battery storage · UE 2 LTD
180 MWScoping Thorpe Marsh GSP
National Grid (England & Wales)
Oct 2035
North Ray Solar Farm 2
Solar · North Ray Solar Farm 2 Ltd
180 MWScoping Grimsby West GSP
National Grid (England & Wales)
Oct 2035
Norton Solar Farm
Solar · RWE Renewables UK Solar and Storage Limited
180 MWScoping Norton GSP
National Grid (England & Wales)
Oct 2031
Sundhope Wind Farm
Onshore wind · Black Knowe Energy Limited
180 MWScoping Sundhope 132kV Substation
SP Transmission (south Scotland)
May 2033
Assel Valley Extension Wind Farm
Wind + storage · Renantis UK Limited
175 MWScoping Maybole GSP
SP Transmission (south Scotland)
Oct 2037
Galileo 06
Onshore wind · Galileo Empower UK Limited
175 MWScoping Llandyfaelog 132kV Substation
National Grid (England & Wales)
Oct 2037
Merthyr Solar and Battery
Solar · Eew Renewables Ltd
175 MWScoping Cilfynydd 400kV Substation
National Grid (England & Wales)
Oct 2037
Philiphaugh Wind Farm
Onshore wind · Edf Energy Renewables Limited
175 MWScoping Philipaugh Substation
SP Transmission (south Scotland)
May 2033
Upper Greenfields BESS
Battery storage · S4 UK DEV LTD
175 MWScoping New Deer 2 132kV Substation
SSEN Transmission (north Scotland)
Oct 2033
Creag Dhubh Windfarm
Wind + storage · Invenergy Development UK Ltd
171 MWScoping Creag Dhubh Wind Farm and BESS 132kV Substation
SSEN Transmission (north Scotland)
Oct 2033
Limekiln Extension 2
Wind + storage · Boralex Limited
171 MWScoping New Limekiln 132 kV Substation
SSEN Transmission (north Scotland)
Oct 2037
Calderdale Wind Farm 240 MW
Onshore wind · Calderdale Wind Farm Ltd
170 MWScoping Rochdale GSP
National Grid (England & Wales)
Oct 2037
Craiglarie Wind Farm
Wind + storage · Invenergy Development UK Ltd
170 MWScoping Ladyburn 132kV Substation
SP Transmission (south Scotland)
Oct 2037
Elchies Wind Farm
Onshore wind · Elchies Wind Limited
170 MWScoping Elchies 132/33kV Substation
SSEN Transmission (north Scotland)
Nov 2028
Elstree Energy Storage
Battery storage · Elstree Battery Storage Limited
170 MWScoping Letchmore Heath 132kV Substation
National Grid (England & Wales)
Jul 2030
Gresham House Connagill BESS
Battery storage · Energyhubdevelopments Limited
170 MWScoping New Connagill 275/132kV Substation
SSEN Transmission (north Scotland)
Oct 2031
Innerwick BESS
Battery storage · Innerwick Storage Ltd
170 MWScoping Braxbess 400/132kV Collector Substation
SP Transmission (south Scotland)
Jul 2028
Scotsburn Road
Battery storage · Tbc 002 Limited
170 MWScoping Fyrish 275kV Substation
SSEN Transmission (north Scotland)
Oct 2030
Highland Wind Farm
Wind + storage · Highland Wind Farm Limited
168 MWScoping Highland Wind Farm 132/33kV substation
SSEN Transmission (north Scotland)
Oct 2030
Page 20 of 32

Sources: NESO Transmission Entry Capacity (TEC) register and interconnector register (downloaded 8 November 2026); NESO Clean Power 2030 network map (existing and planned circuits, substations and network projects); National Grid Electricity Transmission overhead line routes. Contains data from NESO, licensed under the NESO Open Data Licence, and National Grid open data. Projects are placed at their connection substation, not the generating site; projects at new, unnamed “connection nodes” are listed but not mapped.