United States βΊ Grid βΊ Interconnection queues βΊ Texas
ONSHORE WIND Β· SPPOnshore wind project GEN-2011-036, Swisher County
Onshore wind project GEN-2011-036, Swisher County is a 270 MW onshore wind request withdrawn in the SPP interconnection queue, in Swisher County, Texas, connecting to SPS.
Queue statusWithdrawn / abandoned
- PlanningQueued Jul 2011 (completed)
- Withdrawn / abandonedOct 2011 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- GEN-2011-036
- Grid region
- SPP (Southwest Power Pool)
- Utility / transmission owner
- SPS
- Connection point (POI)
- Tap Amarillo South βΓΓ¬ Swisher County 230kV
- Location
- Swisher County, Texas
- Technology
- Wind: 270 MW
- Total requested
- 270 MW
- Study phase
- WITHDRAWN
- Queue status
- Withdrawn
- Entered queue
- 1 July 2011
- Proposed online date
- June 2014
- Withdrawn
- October 2011
Location
Marker shows the centre of Swisher County; the queue data does not give exact sites.
Other requests in Swisher County
- Hornet Solar II SLFSolar + storage Β· 209 MW Β· agreement signed
- Commodus 2 WindOnshore wind Β· 642 MW Β· in study
- Frye StorageSolar + storage Β· 504 MW Β· in study
- Commodus 2 SolarSolar Β· 502 MW Β· in study
- Stem SolarSolar Β· 200 MW Β· in study
- Solar project GEN-2023-120, Swisher CountySolar Β· 130 MW Β· in study
- Hornet SolarSolar Β· 602 MW Β· built
- Frye SolarSolar + storage Β· 502 MW Β· built
- Comanche Run WindOnshore wind Β· 500 MW Β· withdrawn
- Battery storage project GEN-2019-064, Swisher CountyBattery storage Β· 400 MW Β· withdrawn
- Wildrose WindOnshore wind Β· 303 MW Β· withdrawn
- Lazarus SolarSolar Β· 300 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem