United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Battery storage interconnection queue in the USA (2024 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown41479.4 GW
Active in queue79.4 GW414 requests
Agreement signed6,333 MW40 requests
Withdrawn45579.5 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

414 requests · page 1 of 9
ProjectCapacityStatusLocationRegionQueuedOnline
Battery storage project Q2405, Maricopa County
Battery storage
1,020 MWIn study Maricopa, AZWest Feb 2024target 2033
Battery storage project Q112, San Bernardino County
Battery storage
1,000 MWIn study San Bernardino, CAWest Oct 2024target 2028
Comanche BESS
Battery storage · ENERGOS BESS
614 MWIn study Comanche, TXERCOT Dec 2024target 2028
Lavita BESS
Battery storage · Lavita BESS, LLC
606 MWIn study Bell, TXERCOT Dec 2024target 2028
Hobby BESS I
Battery storage · Airport Storage II LLC
603 MWIn study Harris, TXERCOT Sep 2024target 2027
Toce TX BESS 2
Battery storage · TOCE TX BESS 2, LLC
523 MWIn study Wharton, TXERCOT Feb 2024target 2027
Knight Airport BESS I
Battery storage · Airport Storage I LLC
523 MWIn study Harris, TXERCOT Aug 2024target 2027
Ochoa Energy Storage II
Battery storage · Ochoa Energy Storage II LLC
517 MWIn study Waller, TXERCOT Apr 2024target 2029
Catamount Storage
Battery storage · TOCE TX BESS 3, LLC
515 MWIn study Harris, TXERCOT Sep 2024target 2028
Diamante BESS
Battery storage · Flexen USA LLC
514 MWIn study Grimes, TXERCOT Feb 2024target 2028
Millsing BESS
Battery storage · Millsing BESS
502 MWIn study Grimes, TXERCOT Feb 2024target 2028
Battery storage project Q108, San Bernardino County
Battery storage
500 MWIn study San Bernardino, CAWest Jun 2024target 2028
Battery Storage
Battery storage
500 MWIn study Middlesex, MAISO-NE Jun 2024target 2028
Battery Storage
Battery storage
500 MWIn study Barnstable, MAISO-NE May 2024target 2028
Battery storage project PIS087, Salt Lake County
Battery storage
500 MWIn study Salt Lake, UTWest Sep 2024target 2027
Battery storage project 2024-MP2, Mohave County
Battery storage
500 MWIn study Mohave, AZWest Jan 2024target 2028
Battery storage project IC-1247, Heard County
Battery storage
500 MWAgreement signed Heard, GASoutheast Mar 2024target 2028
Battery storage project Company QQ, Washoe County
Battery storage
500 MWIn study Washoe, NVWest Mar 2024target 2028
Battery storage project 2024-MP1, Mohave County
Battery storage
500 MWIn study Mohave, AZWest Jan 2024target 2028
Gamay Energy Storage
Battery storage · GAMAY ENERGY STORAGE LLC
419 MWAgreement signed Brazoria, TXERCOT Feb 2024target 2027
Bypass BESS II
Battery storage · Bypass BESS II LLC
416 MWIn study Fort Bend, TXERCOT Nov 2024target 2027
Battery storage project Q2413, Pinal County
Battery storage
409 MWIn study Pinal, AZWest Feb 2024target 2027
Bernice Energy Storage
Battery storage · Bernice Energy Storage LLC
403 MWIn study Bexar, TXERCOT Sep 2024target 2027
Corruscant BESS
Battery storage · AEU Battery Project III LLC
402 MWIn study Dickens, TXERCOT Feb 2024target 2027
Battery storage project 620, Bay County
Battery storage · FPL
400 MWIn study Bay, FLSoutheast Jan 2024target 2026
Shallow Seam BESS
Battery storage · Shallow Seam Energy Storage, LLC
400 MWIn study Clearfield, PANYISO Sep 2024target 2029
Battery storage project S0026, Converse County
Battery storage
350 MWIn study Converse, WYWest Feb 2024target 2026
Resilient NY Energy Storage
Battery storage · Resilient NY Storage, LLC by Hanwha Energy USA Holdings Corporation, its Manager
349 MWIn study Richmond, NYNYISO Sep 2024target 2028
Rabbit Hollow Energy Storage
Battery storage · Rabbit Hollow Energy Storage, LLC
342 MWIn study Mitchell, TXERCOT Dec 2024target 2028
Andromeda Storage II
Battery storage
320 MWPaused / redesign Scurry, TXERCOT Aug 2024
Battery storage project S0028, Converse County
Battery storage
320 MWIn study Converse, WYWest Feb 2024target 2026
Andromeda Storage IIB
Battery storage
320 MWPaused / redesign Scurry, TXERCOT Jul 2024
Radian Storage II
Battery storage
320 MWPaused / redesign Brown, TXERCOT Jul 2024
Jade Thunder Storage
Battery storage
320 MWPaused / redesign Scurry, TXERCOT Jul 2024
Battery storage project IC-1279, Coweta County
Battery storage
320 MWAgreement signed Coweta, GASoutheast Apr 2024target 2028
Jade Flash Storage
Battery storage
320 MWPaused / redesign Scurry, TXERCOT Jul 2024
Radian Storage IIB
Battery storage
320 MWPaused / redesign Brown, TXERCOT Jul 2024
Diablo Campo Storage
Battery storage · Diablo Campo Energy Center, LLC
314 MWIn study Goliad, TXERCOT Feb 2024target 2029
Wild Paw Storage
Battery storage · Wild Paw Energy Center, LLC
313 MWIn study Henderson, TXERCOT May 2024target 2028
Clay County Yang Storage
Battery storage · DM-CCY, LLC
308 MWIn study Clay, TXERCOT Dec 2024target 2028
Team Ranch Storage
Battery storage · BAF Storage, LLC
307 MWIn study Tarrant, TXERCOT Jun 2024target 2027
Axtell BESS
Battery storage · Axtell BESS LLC
307 MWIn study Mclennan, TXERCOT Oct 2024target 2029
Copperleaf Energy Storage
Battery storage · Copperleaf Energy Storage, LLC
307 MWIn study Wichita, TXERCOT Nov 2024target 2029
Gilleys Energy Storage
Battery storage · Gilleys Energy Storage, LLC
306 MWIn study Wise, TXERCOT Jun 2024target 2028
McCrae Energy Storage
Battery storage · McCrae Energy Storage, LLC
306 MWAgreement signed Erath, TXERCOT May 2024target 2028
O'Bannion Energy Storage
Battery storage · O'Bannion Energy Storage, LLC
306 MWAgreement signed Jack, TXERCOT May 2024target 2028
Wooderson Energy Storage
Battery storage · Wooderson Energy Storage, LLC
306 MWIn study Jack, TXERCOT May 2024target 2028
Southfork Energy Storage
Battery storage · Southfork Energy Storage, LLC
306 MWIn study Kimble, TXERCOT Jul 2024target 2028
Wander Waters BESS
Battery storage · Wander Waters BESS LLC
304 MWIn study Wilbarger, TXERCOT Mar 2024target 2027
Blue Spruce Storage
Battery storage · Blue Spruce Storage LLC
300 MWIn study Bronx, NYNYISO Aug 2024target 2028
Page 1 of 9

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)