United States › Grid › Interconnection queues
OCTARY USA · INTERCONNECTION QUEUESQueue requests in study in the USA (2019 requests)
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Solar + storage project Q68, Los Angeles County Solar + storage |
2,400 MW | In study |
| Onshore wind project Q320, San Juan County Onshore wind |
1,500 MW | Paused / redesign |
| Arida 2 Solar Farm Solar + storage |
1,400 MW | In study |
| Solar + storage project G0615, Sherman County Solar + storage |
1,200 MW | In study |
| Onshore wind project Q318, San Juan County Onshore wind |
1,000 MW | Paused / redesign |
| Onshore wind project Q319, San Juan County Onshore wind |
1,000 MW | Paused / redesign |
| Hoodini Solar + storage |
910 MW | In study |
| Cvow 2, Oss 2 ‚Äì T2G07 Offshore wind · Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) |
836 MW | In study |
| Cvow 1, Oss 1 - T1L11 Offshore wind · Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) |
833 MW | In study |
| Cvow 3, Oss 3 ‚Äì T3G15 Offshore wind · Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) |
820 MW | In study |
| Other project Company KD, White Pine County Other |
750 MW | Paused / redesign |
| Solar + storage project Q317, Coconino County Solar + storage |
750 MW | In study |
| Onshore wind project 366, Rosebud County Onshore wind |
600 MW | Paused / redesign |
| Onshore wind project C006, Wheatland County Onshore wind |
600 MW | In study |
| Onshore wind project 361, Wheatland County Onshore wind |
600 MW | In study |
| Chesterfield CT Units 1 and 2 Gas · Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) |
569 MW | In study |
| Harley Hand Solar Solar + storage · HECTATE ENERGY HARLEY HAND SOLAR LLC |
506 MW | In study |
| Wind + storage project Q311, Navajo County Wind + storage |
500 MW | In study |
| Solar + storage project Q28, Maricopa County Solar + storage |
500 MW | In study |
| Onshore wind project G0619, Wasco County Onshore wind |
500 MW | In study |
| Solar + storage project Q67, Clark County Solar + storage |
500 MW | In study |
| Cider Solar Solar · Hecate Energy Cider Solar LLC |
500 MW | In study |
| Solar project Q312, Coconino County Solar |
500 MW | In study |
| Dragan Solar Solar + storage · Hecate Comanche Solar LLC |
411 MW | In study |
| Onshore wind project 367, Rosebud County Onshore wind |
400 MW | Paused / redesign |
| Solar + storage project Company JX, Pershing County Solar + storage |
340 MW | Paused / redesign |
| Mountaineer Solar Solar · Mustang Mountaineer Solar LLC |
332 MW | In study |
| Onshore wind project 71, Meagher County Onshore wind |
300 MW | Paused / redesign |
| Onshore wind project C007, Meagher County Onshore wind |
300 MW | In study |
| Onshore wind project 362, Wheatland County Onshore wind |
300 MW | Paused / redesign |
| Steward Creek Solar Solar · Steward Creek Solar, LLC |
300 MW | In study |
| Battery storage project Q314, Maricopa County Battery storage |
300 MW | In study |
| Solar + storage project 2019-G1, Butte County Solar + storage |
300 MW | In study |
| Three Lakes Solar Solar + storage · Three Lakes Solar LLC |
300 MW | In study |
| Diversion Wind Onshore wind |
300 MW | Paused / redesign |
| Solar + storage project G0617, Sherman County Solar + storage |
300 MW | In study |
| Black Diamond Solar Solar · Black Diamond Solar Power, LLC |
299 MW | In study |
| Impala Flats Wind Onshore wind · Antelope Flats Wind, LLC |
282 MW | In study |
| Blue Hills Wind Onshore wind |
276 MW | Paused / redesign |
| Charolais Solar Solar + storage · RWE Solar Development, LLC |
262 MW | In study |
| Vermilion Grove Wind Onshore wind · Vermilion Grove Wind, LLC |
255 MW | In study |
| Velociraptor Solar I Solar + storage · Greyhound Solar 2 |
252 MW | In study |
| Onshore wind project J1485, Deuel County Onshore wind |
250 MW | In study |
| Solar project GI-2019-6, Pueblo County Solar |
240 MW | In study |
| Solar + storage project 551, Elmore County Solar + storage · Bennett Solar B LLC |
240 MW | Paused / redesign |
| Thundering Springs Solar + storage |
240 MW | In study |
| Rich Road Solar Energy Center Solar + storage · Rich Road Solar Energy Center, LLC |
240 MW | In study |
| Carol Solar Solar |
223 MW | Paused / redesign |
| Sisters Storage Solar + storage · 174 Power Global Properties |
209 MW | In study |
| Pearl Crescent Solar Solar + storage · RWE Solar Development, LLC |
208 MW | In study |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
- West (non-ISO utilities)46 · 17.8 GW
- PJM (Mid-Atlantic, Midwest)60 · 7,820 MW
- ERCOT (Texas)38 · 5,908 MW
- NYISO (New York)31 · 2,705 MW
- CAISO (California)3 · 2,352 MW
- Southeast (non-ISO utilities)12 · 1,469 MW
- MISO (Midcontinent)7 · 1,168 MW
- SPP (Southwest Power Pool)5 · 558 MW
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)