United States β€Ί Grid β€Ί Interconnection queues β€Ί Wisconsin

OCTARY USA Β· INTERCONNECTION QUEUES

Interconnection queue in Wisconsin (2025 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown2411.0 GW
Active in queue11.0 GW24 requests
Agreement signed0.0 MW0 requests
Withdrawn51,281 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

24 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Red Oak Ridge Energy Center
Gas Β· Invenergy
1,211 MWIn study Kenosha, WIMISO Aug 2025target 2027
Gas project E0016, Calumet County
Gas Β· Invenergy
1,211 MWIn study Calumet, WIMISO Aug 2025target 2027
Gas project J4164, Dane County
Gas
1,203 MWIn study Dane, WIMISO Sep 2025target 2030
Gas project J4165, Kenosha County
Gas
1,203 MWIn study Kenosha, WIMISO Sep 2025target 2030
Gas project J4014, Calumet County
Gas
1,203 MWIn study Calumet, WIMISO May 2025target 2030
Gas project J4116, Walworth County
Gas
950 MWIn study Walworth, WIMISO Oct 2025target 2030
Gas project J4115, Fond Du Lac County
Gas
525 MWIn study Fond Du Lac, WIMISO Oct 2025target 2028
Gas project J4144, Columbia County
Gas
525 MWIn study Columbia, WIMISO Oct 2025target 2030
Gas project E0037, Sheboygan County
Gas Β· Wisconsin Power and Light Company (WPL)
455 MWIn study Sheboygan, WIMISO Aug 2025target 2025
Gas project E0038, Winnebago County
Gas Β· Wisconsin Power and Light Company (WPL)
455 MWIn study Winnebago, WIMISO Aug 2025target 2025
Solar project J3975, Rusk County
Solar
417 MWIn study Rusk, WIMISO Mar 2025target 2030
Gas project J4028, Walworth County
Gas
324 MWIn study Walworth, WIMISO May 2025target 2027
Battery storage project J3006, Milwaukee County
Battery storage
300 MWIn study Milwaukee, WIMISO Jul 2025target 2028
Solar project J4069, Marathon County
Solar
170 MWIn study Marathon, WIMISO Oct 2025target 2030
Gas project J3936, Kenosha County
Gas
132 MWIn study Kenosha, WIMISO Feb 2025target 2027
Surplus; J1316
Gas
132 MWIn study Kenosha, WIMISO Jan 2025target 2026
Solar project J4130, Pepin County
Solar
110 MWIn study Pepin, WIMISO Oct 2025target 2030
Solar project J4127, Barron County
Solar
100 MWIn study Barron, WIMISO Sep 2025target 2029
Surplus; ALTE.QUILTBLCK
Battery storage
98.0 MWIn study Lafayette, WIMISO Mar 2025target 2027
Solar project J2227, Trempealeau County
Solar
89.0 MWIn study Trempealeau, WIMISO Jul 2025target 2024
Solar project J4097, Rock County
Solar
71.5 MWIn study Rock, WIMISO Oct 2025target 2030
Solar project J4101, Jefferson County
Solar
71.0 MWIn study Jefferson, WIMISO Oct 2025target 2028
Surplus; J1751
Solar + storage
50.3 MWIn study Wood, WIMISO May 2025target 2028
Replacing 20 MW of solar with storage; J1746
Other
20.2 MWIn study Columbia, WIMISO Apr 2025target 2026

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)