United States β€Ί Grid β€Ί Interconnection queues β€Ί West Virginia

OCTARY USA Β· INTERCONNECTION QUEUES

Withdrawn queue requests in West Virginia (2021 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown303,315 MW
Active in queue373 MW8 requests
Agreement signed0.0 MW0 requests
Withdrawn303,315 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

30 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project AG2-655, Grant County
Solar Β· Mount Storm Solar, LLC
500 MWWithdrawn / abandoned Grant, WVPJM Mar 2021target 2024
Solar project AG2-466
Solar Β· Hobet Solar I, LLC
330 MWWithdrawn / abandoned WVPJM Mar 2021target 2024
Solar project AH1-625, Webster County
Solar
250 MWWithdrawn / abandoned Webster, WVPJM Sep 2021target 2025
Battery storage project AH1-256, Grant County
Battery storage
240 MWWithdrawn / abandoned Grant, WVPJM Sep 2021target 2025
Mount Storm Repower BESS 1
Battery storage Β· Mount Storm BESS 1 LLC
240 MWWithdrawn / abandoned Grant, WVPJM Sep 2021target 2025
Solar project AG2-686, Nicholas County
Solar
215 MWWithdrawn / abandoned Nicholas, WVPJM Mar 2021target 2024
Solar project AH1-451
Solar
180 MWWithdrawn / abandoned WVPJM Sep 2021target 2025
Solar project AH1-189
Solar Β· Hobet Solar I, LLC
140 MWWithdrawn / abandoned WVPJM Aug 2021target 2025
Battery storage project AG2-689
Battery storage
125 MWWithdrawn / abandoned WVPJM Mar 2021target 2024
Solar project AH1-458, Hampshire County
Solar
100 MWWithdrawn / abandoned Hampshire, WVPJM Sep 2021target 2024
Solar project AG2-656, Kanawha County
Solar
100 MWWithdrawn / abandoned Kanawha, WVPJM Mar 2021target 2024
Battery storage project AH1-252, Barbour County
Battery storage
100 MWWithdrawn / abandoned Barbour, WVPJM Sep 2021target 2024
Solar + storage project AG2-354, Mingo County
Solar + storage Β· Mountaineer Solar LLC
100 MWWithdrawn / abandoned Mingo, WVPJM Mar 2021target 2024
Solar + storage project AG2-464, Jefferson County
Solar + storage
80.0 MWWithdrawn / abandoned Jefferson, WVPJM Mar 2021target 2025
Battery storage project AG2-314, Nicholas County
Battery storage Β· Deep Lake Energy Center, LLC
67.0 MWWithdrawn / abandoned Nicholas, WVPJM Mar 2021target 2024
Solar project AH1-593, Preston County
Solar
65.0 MWWithdrawn / abandoned Preston, WVPJM Sep 2021target 2024
Solar + storage project AG2-509
Solar + storage Β· IRGAH Renewables Development LLC
55.0 MWWithdrawn / abandoned WVPJM Mar 2021target 2024
Battery storage project AH1-459, Hampshire County
Battery storage
50.0 MWWithdrawn / abandoned Hampshire, WVPJM Sep 2021target 2024
Solar project AG2-472, Preston County
Solar
50.0 MWWithdrawn / abandoned Preston, WVPJM Mar 2021target 2025
Messenger Brothers Solar I
Solar Β· RWE Solar Development, LLC
50.0 MWWithdrawn / abandoned Grant, WVPJM Sep 2021target 2024
Messenger Brothers Solar II
Solar Β· RWE Solar Development, LLC
50.0 MWWithdrawn / abandoned Grant, WVPJM Sep 2021target 2024
Messenger Brothers Storage
Battery storage Β· RWE Solar Development, LLC
45.0 MWWithdrawn / abandoned Grant, WVPJM Sep 2021target 2024
Battery storage project AH1-369, Tucker County
Battery storage
40.0 MWWithdrawn / abandoned Tucker, WVPJM Sep 2021target 2023
Battery storage project AH1-594, Preston County
Battery storage
32.0 MWWithdrawn / abandoned Preston, WVPJM Sep 2021target 2024
Trillium PV I
Solar Β· Trillium PV I, LLC
28.0 MWWithdrawn / abandoned Greenbrier, WVPJM Sep 2021target 2025
Solar project AH1-010, Grant County
Solar
20.0 MWWithdrawn / abandoned Grant, WVPJM Apr 2021target 2023
Solar project AH1-118, Brooke County
Solar
20.0 MWWithdrawn / abandoned Brooke, WVPJM Aug 2021target 2023
Solar project AH1-011, Brooke County
Solar
20.0 MWWithdrawn / abandoned Brooke, WVPJM Apr 2021target 2023
Solar + storage project AH1-412, Jefferson County
Solar + storage
20.0 MWWithdrawn / abandoned Jefferson, WVPJM Sep 2021target 2025
Solar project AH1-286, Preston County
Solar
3.0 MWWithdrawn / abandoned Preston, WVPJM Sep 2021target 2023

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)