United States βΊ Grid βΊ Interconnection queues βΊ West Virginia
SOLAR + STORAGE Β· PJMSolar + storage project AH1-412, Jefferson County
Solar + storage project AH1-412, Jefferson County is a 20.0 MW solar + storage request withdrawn in the PJM interconnection queue, in Jefferson County, West Virginia, connecting to APS.
Queue statusWithdrawn / abandoned
- PlanningQueued Sep 2021 (completed)
- Withdrawn / abandonedSep 2024 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- AH1-412
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- APS
- Connection point (POI)
- Franklintown 34.5 kV
- Location
- Jefferson County, West Virginia
- Technology
- Solar: 20.0 MW Β· Battery
- Total requested
- 20.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Feasibility Study
- Queue status
- Withdrawn
- Entered queue
- 10 September 2021
- Proposed online date
- October 2025
- Withdrawn
- September 2024
Location
Marker shows the centre of Jefferson County; the queue data does not give exact sites.
Power plants in West Virginia Β· Transmission lines in West Virginia
Other requests in Jefferson County
- RipponSolar Β· 99.0 MW Β· agreement signed
- Franklintown Farm Solar and BESSSolar + storage Β· 80.0 MW Β· agreement signed
- Solar project AH2-030, Jefferson CountySolar Β· 90.0 MW Β· in study
- Battery storage project AH2-031, Jefferson CountyBattery storage Β· 30.0 MW Β· in study
- Blake SolarSolar Β· 80.0 MW Β· built
- Flowing Springs FarmSolar + storage Β· 125 MW Β· withdrawn
- Solar + storage project AG2-464, Jefferson CountySolar + storage Β· 80.0 MW Β· withdrawn
- Wild Hill SolarSolar Β· 77.5 MW Β· withdrawn
- Solar project AF2-114, Jefferson CountySolar Β· 15.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem