πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί West Virginia

SOLAR + STORAGE Β· PJM

Solar + storage project AG2-509

Solar + storage project AG2-509 is a 55.0 MW solar + storage request withdrawn in the PJM interconnection queue, connecting to AEP.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2021 (completed)
  2. Withdrawn / abandonedMar 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
AG2-509
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
AEP
Developer
IRGAH Renewables Development LLC
Connection point (POI)
Robinson 69 kV
Location
West Virginia
Technology
Solar: 55.0 MW Β· Battery
Total requested
55.0 MW
Service type
Network resource (NRIS)
Study phase
In Progress (unknown study)
Queue status
Withdrawn
Entered queue
31 March 2021
Proposed online date
June 2024
Withdrawn
March 2025

Location

No county location in the queue data.

Power plants in West Virginia Β· Transmission lines in West Virginia

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem