United States βΊ Grid βΊ Interconnection queues βΊ Virginia
OCTARY USA Β· INTERCONNECTION QUEUESInterconnection queue in Virginia (2020 requests)
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Courthouse Solar Solar Β· Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) |
167 MW | In study |
| Pulaski Solar Solar |
150 MW | Agreement signed |
| Quarter Horse Solar Solar Β· Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) |
125 MW | Agreement signed |
| Remington BESS Battery storage |
100 MW | Agreement signed |
| Wild Rose Solar Project Solar Β· Wild Rose Solar Project, LLC |
90.0 MW | In study |
| Clover Creek Solar Solar Β· Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) |
90.0 MW | Agreement signed |
| Bear Island Solar Solar + storage |
89.0 MW | Agreement signed |
| Brunswick Battery Storage Battery storage Β· Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) |
75.0 MW | In study |
| Cerulean Solar and Mulberry BESS Battery storage Β· Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) |
75.0 MW | Agreement signed |
| Buchanan County Solar Solar |
75.0 MW | Agreement signed |
| Fiddlers Ridge Wind Facility Onshore wind |
63.3 MW | Agreement signed |
| Cerulean Solar and Mulberry BESS Solar Β· Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) |
62.0 MW | In study |
| Moon Corner Solar Solar Β· Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) |
60.0 MW | In study |
| Amherst Solar Solar |
50.0 MW | Agreement signed |
| Beckett Solar Solar |
50.0 MW | Agreement signed |
| Dulles Solar and BESS Battery storage |
50.0 MW | Agreement signed |
| Waller Solar I Solar |
45.0 MW | Agreement signed |
| Staunton Solar Solar Β· Staunton Solar LLC |
36.0 MW | Agreement signed |
| Gibson Solar I Solar |
34.0 MW | Agreement signed |
| Redbud-Gaylord 34.5 kV Solar |
30.0 MW | Paused / redesign |
| Amelia Energy Facility Solar Β· Amelia Energy Facility, LLC |
25.0 MW | In study |
| Amelia Energy Facility Solar Β· Amelia Energy Facility, LLC |
20.0 MW | In study |
| Horsepen Branch Solar Solar + storage |
20.0 MW | Agreement signed |
| Switchgrass Solar 1 Solar |
20.0 MW | Paused / redesign |
| Reedy Creek Solar + storage |
20.0 MW | Agreement signed |
| Jarratt Energy Facility 2 Solar Β· Jarratt Energy Facility, LLC |
18.0 MW | In study |
| Turkey Solar Solar |
14.0 MW | Agreement signed |
| Fields 2 Solar |
13.5 MW | Agreement signed |
| Scout Storage I Battery storage |
9.0 MW | Paused / redesign |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)