United States › Grid › Interconnection queues › Texas

OCTARY USA · INTERCONNECTION QUEUES

Queue requests in study in Texas (2020 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown6013.9 GW
Active in queue28.9 GW115 requests
Agreement signed14.9 GW54 requests
Withdrawn558,621 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

60 requests · page 1 of 2
ProjectCapacityStatusLocationRegionQueuedOnline
Replace 1163.3 MW of Sabine Units 3, 4 & 1 with 2 on 1 Combined Cycle Gas Turbine facility; Sabine 1
Gas
1,166 MWIn study Orange, TXMISO Aug 2020target 2026
Skylab Solar
Solar · EDF Renewables Development, Inc.
610 MWIn study Wharton, TXERCOT Jun 2020target 2025
Old Aqueduct Solar
Solar + storage · Old Aqueduct Solar
512 MWIn study Hale, TXERCOT Dec 2020target 2028
Tabor Solar
Solar · Quanah Solar LLC
506 MWIn study Hardeman, TXERCOT Sep 2020target 2027
Frye Storage
Solar + storage · Hecate Energy Frye Storage LLC
504 MWIn study Swisher, TXERCOT Sep 2020target 2026
Pinnington Storage
Solar + storage · Hecate Energy Longhorn Storage LLC
503 MWIn study Jack, TXERCOT Dec 2020target 2029
Dragan Storage
Solar + storage · Hecate Grid Dragan Storage LLC
408 MWIn study Comanche, TXERCOT Aug 2020target 2026
Onshore wind project GEN-2020-067, Terry County
Onshore wind
353 MWIn study Terry, TXSPP Apr 2020target 2026
Mensa BESS
Battery storage · BRP Mensa BESS LLC
307 MWIn study Pecos, TXERCOT Jun 2020target 2027
Old Aqueduct Batt
Solar + storage · Old Aqueduct LLC
303 MWIn study Hale, TXERCOT May 2020target 2028
Brantley Branch Batt
Battery storage · Brantley Branch LLC
302 MWIn study Rusk, TXERCOT May 2020target 2029
BRP Passu BESS
Battery storage · BRP Passu BESS LLC
302 MWIn study Wilbarger, TXERCOT Dec 2020target 2028
Crater BESS
Battery storage · BRP Crater BESS LLC
302 MWIn study Howard, TXERCOT May 2020target 2028
Quela BESS
Battery storage · BRP Quela BESS LLC
301 MWIn study Bexar, TXERCOT Sep 2020target 2027
Sandow Solar
Solar · Sandow Lakes Ranch Solar I, LLC
287 MWIn study Milam, TXERCOT Sep 2020target 2028
Sierra Madre Solar
Solar · Sierra Madre Solar LLC
255 MWIn study Zapata, TXERCOT Jan 2020target 2027
Pandora Solar
Solar
252 MWPaused / redesign Wilson, TXERCOT Jan 2020
Cantaloupe Storage
Battery storage
251 MWPaused / redesign Reeves, TXERCOT Dec 2020
Iguala Solar
Solar
250 MWPaused / redesign Victoria, TXERCOT Oct 2020target 2025
Razorbill Solar
Solar + storage · RWE Solar Development, LLC
240 MWIn study Matagorda, TXERCOT Jan 2020target 2027
Pluto Solar
Solar
228 MWPaused / redesign Webb, TXERCOT Jun 2020target 2028
Maratua Solar
Solar · BDPU Solar Maratua, LLC
217 MWPaused / redesign Grimes, TXERCOT Dec 2020target 2029
Alamosa Solar
Solar
210 MWPaused / redesign Wilbarger, TXERCOT Dec 2020target 2025
Val Vista Grid BESS 1
Battery storage · Val Vista Grid, LLC
209 MWIn study Hidalgo, TXERCOT Aug 2020target 2028
BRP Rhine BESS
Battery storage · BRP Rhine BESS LLC
207 MWIn study Ward, TXERCOT Aug 2020target 2028
BRP Volans BESS
Battery storage · BRP Volans BESS LLC
207 MWIn study Winkler, TXERCOT Aug 2020target 2027
BRP Pyxis BESS
Battery storage · BRP Pyxis BESS LLC
207 MWIn study Ward, TXERCOT Sep 2020target 2028
Sepik BESS
Battery storage · BRP Sepik BESS LLC
205 MWIn study Mitchell, TXERCOT Dec 2020target 2028
Kinenos Solar
Solar · Encino del Sol Energy, LLC
203 MWIn study Brooks, TXERCOT Dec 2020target 2026
Loma Pinta Solar
Solar · Loma Pinta Wind Energy, LLC
203 MWIn study La Salle, TXERCOT Jun 2020target 2027
BRP Kabru BESS
Battery storage · BRP Kabru BESS LLC
203 MWIn study Andrews, TXERCOT Oct 2020target 2028
BRP Kamet BESS
Battery storage · BRP Kamet BESS LLC
203 MWIn study Andrews, TXERCOT Oct 2020target 2025
BRP Perseus BESS
Battery storage · BRP Perseus BESS LLC
203 MWIn study Nueces, TXERCOT Aug 2020target 2027
Nockenut Springs Solar 3
Solar · Pecan Springs Energy, LLC
201 MWIn study Gonzales, TXERCOT Sep 2020target 2029
BRP Pictor BESS
Battery storage · BRP Pictor BESS LLC
201 MWIn study Crane, TXERCOT Jul 2020target 2025
Morrow Lake Storage
Solar + storage · Morrow Lake Storage, LLC
201 MWIn study Frio, TXERCOT Feb 2020target 2026
Elbus BESS
Battery storage · BRP Elbus BESS LLC
201 MWIn study Caldwell, TXERCOT Dec 2020target 2028
Stem Solar
Solar · Innovative Solar 134, LLC
200 MWIn study Swisher, TXERCOT Feb 2020target 2025
Battery storage project GEN-2020-060, Lubbock County
Battery storage
200 MWIn study Lubbock, TXSPP Apr 2020target 2027
Accalia Point Solar
Solar · Accalia Point Solar LLC
191 MWIn study Cameron, TXERCOT Oct 2020target 2029
Lan Solar SLF
Solar + storage · BR Solar, LLC
182 MWIn study Lamar, TXERCOT May 2020target 2028
Creekfield Solar
Solar
161 MWPaused / redesign Fort Bend, TXERCOT Jan 2020
Noria Solar DCC
Solar
145 MWPaused / redesign Nueces, TXERCOT Aug 2020target 2025
BRP Octans BESS
Battery storage · BRP OCTANS BESS LLC
130 MWIn study Pecos, TXERCOT Jul 2020target 2029
BRP Ampato BESS
Battery storage · BRP Ampato BESS LLC
122 MWIn study Crane, TXERCOT Aug 2020target 2027
Kalina Solar
Solar · Aurora Solar LLC
120 MWIn study San Patricio, TXERCOT Aug 2020target 2029
Razorbill Storage
Solar + storage · RWE Solar Development, LLC
120 MWIn study Matagorda, TXERCOT Aug 2020target 2027
Atria Solar
Solar · Atria Energy Project, LLC
112 MWIn study Chambers, TXERCOT Oct 2020target 2025
McClure Solar
Solar · McClure Solar LLC
106 MWIn study Palo Pinto, TXERCOT Jun 2020target 2025
Estonian Storage
Other · 249RD 8ME
103 MWPaused / redesign Delta, TXERCOT Jan 2020target 2022
Page 1 of 2

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)