Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown345,119 MW
Active in queue5,119 MW34 requests
Agreement signed262 MW3 requests
Withdrawn8215.6 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

34 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Solar + storage project GEN-2023-102, Woods County
Solar + storage
475 MWIn study Woods, OKSPP Oct 2023target 2029
Onshore wind project GEN-2023-229, Caddo County
Onshore wind
230 MWIn study Caddo, OKSPP Oct 2023target 2029
Onshore wind project GEN-2022-176, Nowata County
Onshore wind
215 MWIn study Nowata, OKSPP Feb 2023target 2028
Battery storage project GEN-2022-155, Oklahoma County
Battery storage
200 MWIn study Oklahoma, OKSPP Feb 2023target 2027
Solar project GEN-2023-038, Coal County
Solar
200 MWIn study Coal, OKSPP Oct 2023target 2026
Solar + storage project GEN-2023-064, Le Flore County
Solar + storage
200 MWIn study Le Flore, OKSPP Oct 2023target 2029
Solar project GEN-2023-035, Grady County
Solar
200 MWIn study Grady, OKSPP Oct 2023target 2026
Battery storage project GEN-2022-143, Marshall County
Battery storage
200 MWIn study Marshall, OKSPP Feb 2023target 2030
Solar project GEN-2023-177, Garvin County
Solar
200 MWIn study Garvin, OKSPP Oct 2023target 2028
Solar project GEN-2023-210, Lincoln County
Solar
191 MWIn study Lincoln, OKSPP Oct 2023target 2026
Solar project GEN-2023-205, Hughes County
Solar
180 MWIn study Hughes, OKSPP Oct 2023target 2028
Battery storage project GEN-2022-136, Bryan County
Battery storage
180 MWIn study Bryan, OKSPP Feb 2023target 2030
Battery storage project GEN-2022-145, Johnston County
Battery storage
180 MWIn study Johnston, OKSPP Feb 2023target 2030
Battery storage project GEN-2022-235, Canadian County
Battery storage
150 MWIn study Canadian, OKSPP Feb 2023target 2028
Battery storage project GEN-2023-057, Pawnee County
Battery storage
150 MWIn study Pawnee, OKSPP Oct 2023target 2028
Battery storage project GEN-2022-238, Pottawatomie County
Battery storage
150 MWIn study Pottawatomie, OKSPP Feb 2023target 2028
Solar + storage project GEN-2023-063, Rogers County
Solar + storage
135 MWIn study Rogers, OKSPP Oct 2023target 2028
Solar + storage project GEN-2023-092, Choctaw County
Solar + storage
125 MWIn study Choctaw, OKSPP Oct 2023target 2028
Battery storage project GEN-2023-SR22, Mayes County
Battery storage
125 MWIn study Mayes, OKSPP Jun 20232024
Battery storage project GEN-2023-SR20, Custer County
Battery storage
120 MWIn study Custer, OKSPP Jun 20232025
Onshore wind project GEN-2023-088, Okfuskee County
Onshore wind
117 MWIn study Okfuskee, OKSPP Oct 2023target 2028
Solar project GEN-2022-104, Bryan County
Solar
113 MWIn study Bryan, OKSPP Jan 2023target 2028
Battery storage project GEN-2023-SR27, Mayes County
Battery storage
102 MWIn study Mayes, OKSPP Jul 20232024
Battery storage project GEN-2023-055, Mayes County
Battery storage
100 MWIn study Mayes, OKSPP Oct 2023target 2028
Battery storage project GEN-2022-154, Cleveland County
Battery storage
100 MWIn study Cleveland, OKSPP Feb 2023target 2027
Solar + storage project GEN-2023-104, Woods County
Solar + storage
100 MWIn study Woods, OKSPP Oct 2023target 2028
Battery storage project GEN-2022-156, Creek County
Battery storage
100 MWIn study Creek, OKSPP Feb 2023target 2027
Solar + storage project GEN-2023-069, Atoka County
Solar + storage
100 MWIn study Atoka, OKSPP Oct 2023target 2028
Gas project GEN-2023-GR1, Caddo County
Gas
97.5 MWAgreement signed Caddo, OKSPP Jan 20232025
Gas project GEN-2023-GR2, Oklahoma County
Gas
94.2 MWAgreement signed Oklahoma, OKSPP Feb 2023target 2026
Battery storage project GEN-2023-161, Blaine County
Battery storage
74.9 MWIn study Blaine, OKSPP Oct 2023target 2027
Battery storage project GEN-2023-SR25, Mayes County
Battery storage
72.5 MWIn study Mayes, OKSPP Jul 20232024
Battery storage project GEN-2023-SR26, Mayes County
Battery storage
72.5 MWIn study Mayes, OKSPP Jul 20232024
Battery storage project GEN-2023-SR16, Woodward County
Battery storage
70.0 MWAgreement signed Woodward, OKSPP Apr 20232025

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)