United States โ€บ Grid โ€บ Interconnection queues โ€บ Massachusetts

OCTARY USA ยท INTERCONNECTION QUEUES

Withdrawn queue requests in Massachusetts (2022 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown657,262 MW
Active in queue549 MW3 requests
Agreement signed249 MW2 requests
Withdrawn657,262 MW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

65 requests ยท page 1 of 2
ProjectCapacityStatusLocationRegionQueuedOnline
Offshore Wind
Offshore wind
1,200 MWWithdrawn / abandoned MAISO-NE Feb 2022target 2029
Offshore Wind
Offshore wind
1,200 MWWithdrawn / abandoned MAISO-NE Dec 2022target 2029
Offshore Wind
Offshore wind
1,200 MWWithdrawn / abandoned MAISO-NE Aug 2022target 2029
Offshore Wind
Offshore wind
470 MWWithdrawn / abandoned MAISO-NE Sep 2022target 2029
Battery Storage
Battery storage
315 MWWithdrawn / abandoned Essex, MAISO-NE Apr 2022target 2032
Battery Storage
Battery storage
300 MWWithdrawn / abandoned Hampden, MAISO-NE Nov 2022target 2025
Battery Storage
Battery storage
293 MWWithdrawn / abandoned Bristol, MAISO-NE Dec 2022target 2027
Battery Storage
Battery storage
275 MWWithdrawn / abandoned Hampden, MAISO-NE Dec 2022target 2027
Battery Storage
Battery storage
270 MWWithdrawn / abandoned Norfolk, MAISO-NE Oct 2022target 2023
Battery Storage
Battery storage
257 MWWithdrawn / abandoned Bristol, MAISO-NE Dec 2022target 2027
Battery Storage
Battery storage
206 MWWithdrawn / abandoned Bristol, MAISO-NE Nov 2022target 2027
Battery Storage
Battery storage
158 MWWithdrawn / abandoned Worcester, MAISO-NE Aug 2022target 2027
Battery Storage
Battery storage
155 MWWithdrawn / abandoned Bristol, MAISO-NE Apr 2022target 2026
Battery Storage
Battery storage
130 MWWithdrawn / abandoned Worcester, MAISO-NE Nov 2022target 2026
Battery Storage
Battery storage
130 MWWithdrawn / abandoned Berkshire, MAISO-NE Nov 2022target 2026
Battery Storage
Battery storage
119 MWWithdrawn / abandoned Berkshire, MAISO-NE Sep 2022target 2025
Battery Storage
Battery storage
117 MWWithdrawn / abandoned Bristol, MAISO-NE Dec 2022target 2027
Battery Storage
Battery storage
95.0 MWWithdrawn / abandoned Worcester, MAISO-NE Jul 2022target 2023
Battery Storage
Battery storage
20.0 MWWithdrawn / abandoned Bristol, MAISO-NE Mar 2022target 2024
Battery Storage
Battery storage
20.0 MWWithdrawn / abandoned Bristol, MAISO-NE Mar 2022target 2024
Battery Storage
Battery storage
20.0 MWWithdrawn / abandoned Berkshire, MAISO-NE Jun 2022target 2027
Battery Storage
Battery storage
20.0 MWWithdrawn / abandoned Bristol, MAISO-NE Mar 2022target 2024
Battery Storage
Battery storage
18.9 MWWithdrawn / abandoned Hampshire, MAISO-NE Jul 2022target 2023
Group @ Hatchville 936 - EMA ASO
Solar + storage
18.5 MWWithdrawn / abandoned Barnstable, MAISO-NE Jun 2022target 2023
Group @ Medway 65 - EMA ASO
Solar + storage
17.5 MWWithdrawn / abandoned Middlesex, MAISO-NE Jan 2022target 2023
Group @ Industrial Park 636 - EMA ASO
Solar + storage
16.5 MWWithdrawn / abandoned Bristol, MAISO-NE Jun 2022target 2023
Group @ Wing Lane 624 - EMA ASO
Solar + storage
15.0 MWWithdrawn / abandoned Bristol, MAISO-NE Jun 2022target 2023
Battery Storage
Battery storage
11.9 MWWithdrawn / abandoned Franklin, MAISO-NE Sep 2022target 2027
Group @ Orleans 975 - EMA ASO
Solar + storage
10.0 MWWithdrawn / abandoned Barnstable, MAISO-NE Jun 2022target 2023
Battery Storage
Battery storage
10.0 MWWithdrawn / abandoned Worcester, MAISO-NE Sep 2022target 2025
Battery Storage
Battery storage
10.0 MWWithdrawn / abandoned Worcester, MAISO-NE Jan 2022target 2022
Group @ Montigue - WMA ASO
Solar + storage
9.9 MWWithdrawn / abandoned Franklin, MAISO-NE Jan 2022target 2023
Battery Storage
Battery storage
9.1 MWWithdrawn / abandoned Franklin, MAISO-NE Sep 2022target 2027
Group @ French King - WMA ASO
Solar + storage
8.9 MWWithdrawn / abandoned Franklin, MAISO-NE Jan 2022target 2023
Group @ Maynard 416 - EMA ASO
Solar + storage
8.5 MWWithdrawn / abandoned Middlesex, MAISO-NE Jan 2022target 2023
Group @ Berkshire 18C
Solar + storage
7.7 MWWithdrawn / abandoned Hampden, MAISO-NE Jan 2022target 2023
Group @ Podick - WMA ASO
Solar + storage
7.7 MWWithdrawn / abandoned Hampden, MAISO-NE Jan 2022target 2023
Group @ Blandford 19J - WMA ASO
Solar + storage
7.0 MWWithdrawn / abandoned Berkshire, MAISO-NE Jan 2022target 2023
Group @ West Pond 737 - EMA ASO
Solar + storage
7.0 MWWithdrawn / abandoned Middlesex, MAISO-NE Jun 2022target 2025
Uxbridge Substation โ€šร„รฌ NG Hopedale West Group Study
Battery storage
7.0 MWWithdrawn / abandoned Worcester, MAISO-NE Sep 2022target 2025
Group @ Duxbury 738 - EMA ASO
Solar + storage
6.8 MWWithdrawn / abandoned Plymouth, MAISO-NE Jun 2022target 2023
Canton 470 - EMA ASO
Solar + storage
5.0 MWWithdrawn / abandoned Norfolk, MAISO-NE Jun 2022target 2023
Holliston 130 - EMA ASO
Battery storage
5.0 MWWithdrawn / abandoned Middlesex, MAISO-NE Jan 2022target 2023
Tremont 713 - EMA ASO
Solar + storage
5.0 MWWithdrawn / abandoned Plymouth, MAISO-NE Jun 2022target 2025
Cumberland 22B - WMA ASO
Solar + storage
5.0 MWWithdrawn / abandoned Hampden, MAISO-NE Jan 2022target 2023
Hyannis 961 - EMA ASO
Solar + storage
5.0 MWWithdrawn / abandoned Barnstable, MAISO-NE Jun 2022target 2023
Uxbridge Substation โ€šร„รฌ NG Hopedale West Group Study
Battery storage
5.0 MWWithdrawn / abandoned Worcester, MAISO-NE Sep 2022target 2025
Whitins Pond Substation โ€šร„รฌ NG Hopedale West Group Study
Battery storage
4.9 MWWithdrawn / abandoned Worcester, MAISO-NE Sep 2022target 2025
Whitins Pond Substation โ€šร„รฌ NG Hopedale West Group Study
Battery storage
4.9 MWWithdrawn / abandoned Worcester, MAISO-NE Sep 2022target 2025
Marshfield 739 - EMA ASO
Solar + storage
4.6 MWWithdrawn / abandoned Plymouth, MAISO-NE Jun 2022target 2023
Page 1 of 2

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)