BATTERY STORAGE · ISO-NE

Battery Storage

Battery Storage is a 206 MW battery storage request withdrawn in the ISO-NE interconnection queue, in Bristol County, Massachusetts.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Nov 2022 (completed)
  2. Withdrawn / abandonedOct 2024 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
1335
Grid region
ISO-NE (New England)
Connection point (POI)
Non-PTF 115KV lines ET and W owned by TMLP between Cleary Flood Substation and Substation #16 (W Water St), approximately 1.26 miles from Cleary Flood. Project would interconnect half of the net MW ca
Location
Bristol County, Massachusetts
Technology
Battery: 206 MW
Total requested
206 MW
Service type
Network resource (NRIS)
Study phase
System Impact Study
Queue status
Withdrawn
Entered queue
10 November 2022
Proposed online date
April 2027
Withdrawn
October 2024

Location

Marker shows the centre of Bristol County; the queue data does not give exact sites.

Power plants in Massachusetts · Transmission lines in Massachusetts

Other requests in Bristol County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem