BATTERY STORAGE · ISO-NE

Battery Storage

Battery Storage is a 9.1 MW battery storage request withdrawn in the ISO-NE interconnection queue, in Franklin County, Massachusetts.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Sep 2022 (completed)
  2. Withdrawn / abandonedMar 2023 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
1302
Grid region
ISO-NE (New England)
Connection point (POI)
Eversource 21C1, Montague Substation,13.8 kV
Location
Franklin County, Massachusetts
Technology
Battery: 9.1 MW
Total requested
9.1 MW
Service type
Network resource (NRIS)
Study phase
Feasibility Study
Queue status
Withdrawn
Entered queue
22 September 2022
Proposed online date
May 2027
Withdrawn
March 2023

Location

Marker shows the centre of Franklin County; the queue data does not give exact sites.

Power plants in Massachusetts · Transmission lines in Massachusetts

Other requests in Franklin County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem