United States β€Ί Grid β€Ί Interconnection queues β€Ί Maine

OCTARY USA Β· INTERCONNECTION QUEUES

Withdrawn queue requests in Maine (2022 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown153,253 MW
Active in queue160 MW1 requests
Agreement signed160 MW1 requests
Withdrawn153,253 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

15 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Wind
Onshore wind
905 MWWithdrawn / abandoned Aroostook, MEISO-NE May 2022target 2026
Wind
Onshore wind
500 MWWithdrawn / abandoned Aroostook, MEISO-NE Jan 2022target 2025
Wind
Onshore wind
500 MWWithdrawn / abandoned Aroostook, MEISO-NE Jan 2022target 2026
Solar
Solar
319 MWWithdrawn / abandoned Aroostook, MEISO-NE May 2022target 2026
Solar
Solar
300 MWWithdrawn / abandoned Aroostook, MEISO-NE Mar 2022target 2026
Solar plus Battery
Solar + storage
205 MWWithdrawn / abandoned Aroostook, MEISO-NE Aug 2022target 2025
Solar plus Battery
Solar + storage
129 MWWithdrawn / abandoned Oxford, MEISO-NE Mar 2022target 2029
Solar
Solar
75.3 MWWithdrawn / abandoned Washington, MEISO-NE Jul 2022target 2026
Solar
Solar
75.0 MWWithdrawn / abandoned Franklin, MEISO-NE Mar 2022target 2025
Detroit/Guilford/Belfast DG Area Study
Solar + storage
57.7 MWWithdrawn / abandoned Piscataquis, MEISO-NE May 2022target 2027
Solar Increase (QP1145)
Solar
54.1 MWWithdrawn / abandoned Hancock, MEISO-NE Aug 2022target 2026
Lewiston CMP Cluster 5
Solar + storage
52.5 MWWithdrawn / abandoned Oxford, MEISO-NE Mar 2022target 2028
Battery Storage
Battery storage
50.7 MWWithdrawn / abandoned York, MEISO-NE Apr 2022target 2024
Sanford/Quaker Hill CMP Cluster 4
Solar + storage
21.2 MWWithdrawn / abandoned York, MEISO-NE Mar 2022target 2028
Kimball DG Area Study
Solar + storage
7.9 MWWithdrawn / abandoned York, MEISO-NE May 2022target 2028

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)