United States β€Ί Grid β€Ί Interconnection queues β€Ί Maine

OCTARY USA Β· INTERCONNECTION QUEUES

Withdrawn queue requests in Maine (2020 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown271,274 MW
Active in queue129 MW4 requests
Agreement signed129 MW4 requests
Withdrawn271,274 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

27 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Battery Storage
Battery storage
200 MWWithdrawn / abandoned Androscoggin, MEISO-NE Jan 2020target 2022
Solar
Solar
120 MWWithdrawn / abandoned Penobscot, MEISO-NE May 2020target 2023
Battery Storage
Battery storage
112 MWWithdrawn / abandoned Penobscot, MEISO-NE Apr 2020target 2024
Battery Storage
Battery storage
112 MWWithdrawn / abandoned Penobscot, MEISO-NE Apr 2020target 2024
Battery Storage
Battery storage
102 MWWithdrawn / abandoned Kennebec, MEISO-NE Nov 2020target 2023
Solar
Solar
100 MWWithdrawn / abandoned Penobscot, MEISO-NE Nov 2020target 2024
Solar
Solar
100 MWWithdrawn / abandoned Penobscot, MEISO-NE Sep 2020target 2024
Solar
Solar
100 MWWithdrawn / abandoned Penobscot, MEISO-NE Oct 2020target 2024
Solar
Solar
90.0 MWWithdrawn / abandoned Oxford, MEISO-NE May 2020target 2021
Solar
Solar
65.0 MWWithdrawn / abandoned Oxford, MEISO-NE Oct 2020target 2024
Solar
Solar
40.0 MWWithdrawn / abandoned Androscoggin, MEISO-NE Mar 2020target 2022
Solar
Solar
20.0 MWWithdrawn / abandoned Penobscot, MEISO-NE Apr 2020target 2028
Battery Storage
Battery storage
20.0 MWWithdrawn / abandoned Penobscot, MEISO-NE Apr 2020target 2024
Solar
Solar
17.2 MWWithdrawn / abandoned Sagadahoc, MEISO-NE Apr 2020target 2030
Solar
Solar
17.0 MWWithdrawn / abandoned Oxford, MEISO-NE Jan 2020target 2024
Solar
Solar
11.8 MWWithdrawn / abandoned Washington, MEISO-NE Sep 2020target 2023
Augusta E. Side 115 kV SS - Augusta Area Study
Solar
10.0 MWWithdrawn / abandoned Kennebec, MEISO-NE Oct 2020target 2024
Bowman Street 115 kV SS - Augusta Area Study
Solar + storage
5.0 MWWithdrawn / abandoned Kennebec, MEISO-NE Oct 2020target 2023
Solar Increase
Solar
5.0 MWWithdrawn / abandoned Androscoggin, MEISO-NE Apr 2020target 2021
Solar
Solar
5.0 MWWithdrawn / abandoned Androscoggin, MEISO-NE Feb 2020target 2021
Puddledock Road 115 kV SS - Augusta Area Study
Solar
4.9 MWWithdrawn / abandoned Kennebec, MEISO-NE Oct 2020target 2024
Puddledock Road 115 kV SS - Augusta Area Study
Solar
4.9 MWWithdrawn / abandoned Kennebec, MEISO-NE Oct 2020target 2023
Solar
Solar
4.0 MWWithdrawn / abandoned Washington, MEISO-NE Apr 2020target 2021
Puddledock Road 115 kV SS - Augusta Area Study
Solar
2.5 MWWithdrawn / abandoned Kennebec, MEISO-NE Oct 2020target 2023
Augusta E. Side 115 kV SS - Augusta Area Study
Solar
2.0 MWWithdrawn / abandoned Kennebec, MEISO-NE Oct 2020target 2024
Bowman Street 115 kV SS - Augusta Area Study
Solar
1.8 MWWithdrawn / abandoned Sagadahoc, MEISO-NE Oct 2020target 2023
Bowman Street 115 kV SS - Augusta Area Study
Solar
1.7 MWWithdrawn / abandoned Kennebec, MEISO-NE Oct 2020target 2023

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)