United States β€Ί Grid β€Ί Interconnection queues β€Ί Maine

SOLAR Β· ISO-NE

Solar

Solar is a 5.0 MW solar request withdrawn in the ISO-NE interconnection queue, in Androscoggin County, Maine.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Feb 2020 (completed)
  2. Withdrawn / abandonedApr 2020 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
952
Grid region
ISO-NE (New England)
Connection point (POI)
CMP 34.5kV line. 44.074807, -70.280400
Location
Androscoggin County, Maine
Technology
Solar: 5.0 MW
Total requested
5.0 MW
Service type
Energy only (ERIS)
Queue status
Withdrawn
Entered queue
18 February 2020
Proposed online date
September 2021
Withdrawn
April 2020

Location

Marker shows the centre of Androscoggin County; the queue data does not give exact sites.

Power plants in Maine Β· Transmission lines in Maine

Other requests in Androscoggin County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem