United States βΊ Grid βΊ Interconnection queues βΊ Maine
SOLAR Β· ISO-NESolar Increase
Solar Increase is a 5.0 MW solar request withdrawn in the ISO-NE interconnection queue, in Androscoggin County, Maine.
Queue statusWithdrawn / abandoned
- PlanningQueued Apr 2020 (completed)
- Withdrawn / abandonedAug 2020 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 1025
- Grid region
- ISO-NE (New England)
- Connection point (POI)
- 34.5 kV line from Gulf island to Crowleys substation. 102159-97000-101460
- Location
- Androscoggin County, Maine
- Technology
- Solar: 5.0 MW
- Total requested
- 5.0 MW
- Service type
- Network resource (NRIS)
- Queue status
- Withdrawn
- Entered queue
- 27 April 2020
- Proposed online date
- November 2021
- Withdrawn
- August 2020
Location
Marker shows the centre of Androscoggin County; the queue data does not give exact sites.
Other requests in Androscoggin County
- Green Apple SolarSolar Β· 179 MW Β· agreement signed
- BD Solar Church HillSolar Β· 20.0 MW Β· agreement signed
- Turner Meadow SolarSolar Β· 19.8 MW Β· agreement signed
- Riley-Jay-Otis-LivermoreHydro Β· 28.3 MW Β· built
- SolarSolar Β· 20.0 MW Β· built
- Gulf Island Unit 2 IncreaseHydro Β· 4.4 MW Β· built
- Gulf Island Unit 1 IncreaseHydro Β· 1.0 MW Β· built
- Battery StorageBattery storage Β· 200 MW Β· withdrawn
- SolarSolar Β· 40.0 MW Β· withdrawn
- SolarSolar Β· 15.0 MW Β· withdrawn
- SolarSolar Β· 15.0 MW Β· withdrawn
- SolarSolar Β· 10.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem