SOLAR Β· ISO-NE

Solar Increase

Solar Increase is a 5.0 MW solar request withdrawn in the ISO-NE interconnection queue, in Androscoggin County, Maine.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2020 (completed)
  2. Withdrawn / abandonedAug 2020 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
1025
Grid region
ISO-NE (New England)
Connection point (POI)
34.5 kV line from Gulf island to Crowleys substation. 102159-97000-101460
Location
Androscoggin County, Maine
Technology
Solar: 5.0 MW
Total requested
5.0 MW
Service type
Network resource (NRIS)
Queue status
Withdrawn
Entered queue
27 April 2020
Proposed online date
November 2021
Withdrawn
August 2020

Location

Marker shows the centre of Androscoggin County; the queue data does not give exact sites.

Power plants in Maine Β· Transmission lines in Maine

Other requests in Androscoggin County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem