United States › Grid › Interconnection queues › Maine
SOLAR · ISO-NEBowman Street 115 kV SS - Augusta Area Study
Bowman Street 115 kV SS - Augusta Area Study is a 1.7 MW solar request withdrawn in the ISO-NE interconnection queue, in Kennebec County, Maine, connecting to CMP.
Queue statusWithdrawn / abandoned
- PlanningQueued Oct 2020 (completed)
- Withdrawn / abandonedJun 2025 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 1072
- Grid region
- ISO-NE (New England)
- Utility / transmission owner
- CMP
- Connection point (POI)
- CMP CAPITOL STREET Substation, Circuit 215D3
- Location
- Kennebec County, Maine
- Technology
- Solar: 1.7 MW
- Total requested
- 1.7 MW
- Queue status
- Withdrawn
- Entered queue
- 2 October 2020
- Proposed online date
- June 2023
- Withdrawn
- June 2025
Location
Marker shows the centre of Kennebec County; the queue data does not give exact sites.
Other requests in Kennebec County
- SolarSolar · 7.0 MW · agreement signed
- Bowman Street 115 kV SS - Augusta Area StudySolar + storage · 9.9 MW · built
- Bowman Street 115 kV SS - Augusta Area StudySolar + storage · 9.5 MW · built
- SolarSolar · 7.2 MW · built
- Augusta E. Side 115 kV SS - Augusta Area StudySolar + storage · 4.3 MW · built
- Augusta E. Side 115 kV SS - Augusta Area StudySolar · 4.0 MW · built
- Augusta E. Side 115 kV SS - Augusta Area StudySolar + storage · 3.8 MW · built
- Bowman Street 115 kV SS - Augusta Area StudySolar · 3.3 MW · built
- Battery StorageBattery storage · 102 MW · withdrawn
- Winslow-County Rd Lakewood 115 kV SS - Winslow-County Rd-Lakewood 2 DG StudySolar · 21.0 MW · withdrawn
- SolarSolar · 20.0 MW · withdrawn
- SolarSolar · 20.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem