πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Maine

SOLAR Β· ISO-NE

Solar

Solar is a 7.2 MW solar request built and operating in the ISO-NE interconnection queue, in Kennebec County, Maine, connecting to CMP.

Queue statusOperating
  1. PlanningQueued Aug 2019 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingTarget Jul 2021 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
902
Grid region
ISO-NE (New England)
Utility / transmission owner
CMP
Connection point (POI)
CMP Blair Road substation, Circuit207D2
Location
Kennebec County, Maine
Technology
Solar: 7.2 MW
Total requested
7.2 MW
Study phase
IA Executed
Queue status
Operational
Entered queue
1 August 2019
Proposed online date
July 2021

Location

Marker shows the centre of Kennebec County; the queue data does not give exact sites.

Power plants in Maine Β· Transmission lines in Maine

Other requests in Kennebec County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem