Solar is a 7.2 MW solar request built and operating in the ISO-NE interconnection queue, in Kennebec County, Maine, connecting to CMP.
Request details
- Queue ID
- 902
- Grid region
- ISO-NE (New England)
- Utility / transmission owner
- CMP
- Connection point (POI)
- CMP Blair Road substation, Circuit207D2
- Location
- Kennebec County, Maine
- Technology
- Solar: 7.2 MW
- Total requested
- 7.2 MW
- Study phase
- IA Executed
- Queue status
- Operational
- Entered queue
- 1 August 2019
- Proposed online date
- July 2021
Location
Marker shows the centre of Kennebec County; the queue data does not give exact sites.
Other requests in Kennebec County
- SolarSolar Β· 7.0 MW Β· agreement signed
- Bowman Street 115 kV SS - Augusta Area StudySolar + storage Β· 9.9 MW Β· built
- Bowman Street 115 kV SS - Augusta Area StudySolar + storage Β· 9.5 MW Β· built
- Augusta E. Side 115 kV SS - Augusta Area StudySolar + storage Β· 4.3 MW Β· built
- Augusta E. Side 115 kV SS - Augusta Area StudySolar Β· 4.0 MW Β· built
- Augusta E. Side 115 kV SS - Augusta Area StudySolar + storage Β· 3.8 MW Β· built
- Bowman Street 115 kV SS - Augusta Area StudySolar Β· 3.3 MW Β· built
- Battery StorageBattery storage Β· 102 MW Β· withdrawn
- Winslow-County Rd Lakewood 115 kV SS - Winslow-County Rd-Lakewood 2 DG StudySolar Β· 21.0 MW Β· withdrawn
- SolarSolar Β· 20.0 MW Β· withdrawn
- SolarSolar Β· 20.0 MW Β· withdrawn
- Augusta E/Puddledock/Bowman St 115 kV SS - Midcoast Area DG StudySolar + storage Β· 18.6 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem