United States β€Ί Grid β€Ί Interconnection queues β€Ί Kentucky

OCTARY USA Β· INTERCONNECTION QUEUES

Interconnection queue in Kentucky (2025 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown344,487 MW
Active in queue4,487 MW34 requests
Agreement signed0.0 MW0 requests
Withdrawn9586 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

34 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Gas project AH1-721
Gas Β· East Kentucky Power Cooperative, Inc.
786 MWIn study KYPJM Apr 2025
Gas project LGE-CS2025-002, Jefferson County
Gas
680 MWIn study Jefferson, KYSoutheast Nov 2025target 2031
Battery storage project LGE-CS2025-001, Jefferson County
Battery storage
400 MWIn study Jefferson, KYSoutheast Nov 2025target 2029
Battery storage project 25RSC-005, Mccracken County
Battery storage
250 MWIn study Mccracken, KYSoutheast Jul 2025target 2030
Solar project AG2-184, Knott County
Solar Β· STMO bn, LLC
210 MWIn study Knott, KYPJM Feb 2025target 2024
Battery storage project 25RSC-004, Marshall County
Battery storage
200 MWIn study Marshall, KYSoutheast Jul 2025target 2030
Solar project AH1-617
Solar Β· STMO bn, LLC
200 MWIn study KYPJM Feb 2025target 2024
Solar + storage project LGE-CS2025-004, Lincoln County
Solar + storage
200 MWIn study Lincoln, KYSoutheast Dec 2025target 2029
Surplus; J1450
Other
150 MWIn study Webster, KYMISO Feb 2025target 2026
Solar project J2540, Graves County
Solar
150 MWIn study Graves, KYMISO Oct 2025target 2026
Solar + storage project 25RSC-010, Graves County
Solar + storage
140 MWIn study Graves, KYSoutheast Aug 2025target 2031
Battery storage project LGE-CS2025-003, Crittenden County
Battery storage
125 MWIn study Crittenden, KYSoutheast Dec 2025target 2029
Solar project LGE-CS2025-013, Ballard County
Solar
100 MWIn study Ballard, KYSoutheast Dec 2025target 2028
Surplus; J1638
Battery storage
100 MWIn study Hancock, KYMISO Jan 2025target 2029
Solar project AH1-664, Fleming County
Solar Β· Hummingbird Energy LLC
100 MWIn study Fleming, KYPJM Feb 2025
Solar project AH1-239, Boone County
Solar Β· Clinton Solar, LLC
80.0 MWIn study Boone, KYPJM Mar 2025target 2024
Solar project AH1-666, Fleming County
Solar Β· Fleming Solar, LLC
80.0 MWIn study Fleming, KYPJM Mar 2025
Solar project AH1-665, Fleming County
Solar Β· Hummingbird Energy LLC
80.0 MWIn study Fleming, KYPJM May 2025
Solar + storage project AG2-424, Larue County
Solar + storage Β· Magnolia Solar and Grazing Farm LLC
63.3 MWIn study Larue, KYPJM Mar 2025target 2023
Solar project AG2-073, Madison County
Solar Β· SR Madison, LLC
53.0 MWIn study Madison, KYPJM Mar 2025target 2024
Solar project J2541, Graves County
Solar
50.0 MWIn study Graves, KYMISO Oct 2025target 2026
Solar project AH1-004, Fayette County
Solar Β· SR Fayette, LLC
40.0 MWIn study Fayette, KYPJM Mar 2025target 2023
Solar project AG2-298, Marion County
Solar Β· Crab Run Solar Project, LLC
35.0 MWIn study Marion, KYPJM Mar 2025target 2024
Solar project AG2-081, Montgomery County
Solar Β· SR Fayette II, LLC
30.0 MWIn study Montgomery, KYPJM Mar 2025target 2024
Solar project AH1-570
Solar Β· South Fork Solar, LLC
25.0 MWIn study KYPJM Mar 2025target 2024
Solar project AH1-571
Solar Β· South Fork Solar, LLC
20.0 MWIn study KYPJM Mar 2025target 2024
Gas project LGE-CS2025-011, Trimble County
Gas
19.0 MWIn study Trimble, KYSoutheast Dec 2025target 2029
Gas project LGE-CS2025-012, Trimble County
Gas
19.0 MWIn study Trimble, KYSoutheast Dec 2025target 2030
Gas project LGE-CS2025-008, Trimble County
Gas
17.0 MWIn study Trimble, KYSoutheast Dec 2025target 2026
Gas project LGE-CS2025-006, Trimble County
Gas
17.0 MWIn study Trimble, KYSoutheast Dec 2025target 2026
Gas project LGE-CS2025-005, Trimble County
Gas
17.0 MWIn study Trimble, KYSoutheast Dec 2025target 2026
Gas project LGE-CS2025-007, Trimble County
Gas
17.0 MWIn study Trimble, KYSoutheast Dec 2025target 2026
Gas project LGE-CS2025-010, Trimble County
Gas
17.0 MWIn study Trimble, KYSoutheast Dec 2025target 2026
Gas project LGE-CS2025-009, Trimble County
Gas
17.0 MWIn study Trimble, KYSoutheast Dec 2025target 2026

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)