United States › Grid › Interconnection queues › Kentucky
GAS · SOUTHEASTGas project LGE-CS2025-007, Trimble County
Gas project LGE-CS2025-007, Trimble County is a 17.0 MW gas request in interconnection study in the Southeast interconnection queue, in Trimble County, Kentucky, connecting to Louisville Gas & Electric and Kentucky Utilities Energy.
- PlanningQueued Dec 2025 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Oct 2026 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- LGE-CS2025-007
- Grid region
- Southeast (non-ISO utilities)
- Utility / transmission owner
- Louisville Gas & Electric and Kentucky Utilities Energy
- Connection point (POI)
- Trimble County Switching Station, 345 kV (Unit #7)
- Location
- Trimble County, Kentucky
- Technology
- Gas: 17.0 MW
- Total requested
- 17.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- In Progress (unknown study)
- Queue status
- Active
- Entered queue
- 18 December 2025
- Proposed online date
- October 2026
Location
Marker shows the centre of Trimble County; the queue data does not give exact sites.
Other requests in Trimble County
- Gas project LGE-GIS-2009-004, Trimble CountyGas · 785 MW · agreement signed
- Gas project G018, Trimble CountyGas · 174 MW · in study
- Gas project G016, Trimble CountyGas · 174 MW · in study
- Gas project G017, Trimble CountyGas · 174 MW · in study
- Gas project G069, Trimble CountyGas · 174 MW · in study
- Coal project G003, Trimble CountyCoal · 174 MW · in study
- Coal project G002, Trimble CountyCoal · 174 MW · in study
- Gas project LGE-CS2025-011, Trimble CountyGas · 19.0 MW · in study
- Gas project LGE-CS2025-012, Trimble CountyGas · 19.0 MW · in study
- Gas project LGE-CS2025-008, Trimble CountyGas · 17.0 MW · in study
- Gas project LGE-CS2025-006, Trimble CountyGas · 17.0 MW · in study
- Gas project LGE-CS2025-005, Trimble CountyGas · 17.0 MW · in study
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem