United States โ€บ Grid โ€บ Interconnection queues โ€บ Indiana

OCTARY USA ยท INTERCONNECTION QUEUES

Interconnection queue in Indiana (2022 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown7113.5 GW
Active in queue13.5 GW71 requests
Agreement signed50.0 MW1 requests
Withdrawn10416.2 GW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

71 requests ยท page 1 of 2
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project AH2-348, Daviess County
Solar
700 MWIn study Daviess, INPJM Mar 2022target 2025
Solar project J2846, Pulaski County
Solar
700 MWIn study Pulaski, INMISO Sep 2022target 2025
Solar + storage project J3075, Sullivan County
Solar + storage
560 MWIn study Sullivan, INMISO Sep 2022target 2025
Battery storage project AI1-022, Huntington County
Battery storage
450 MWIn study Huntington, INPJM Apr 2022target 2026
Battery storage project J2496, White County
Battery storage
400 MWIn study White, INMISO Sep 2022target 2026
Solar project AH2-352
Solar
400 MWIn study INPJM Mar 2022target 2026
Solar project AH2-257, Vermillion County
Solar
400 MWIn study Vermillion, INPJM Mar 2022target 2024
Solar + storage project AH2-413, Huntington County
Solar + storage
365 MWIn study Huntington, INPJM Mar 2022target 2026
Battery storage project AH2-414, Huntington County
Battery storage
350 MWIn study Huntington, INPJM Mar 2022target 2026
Battery storage project J2215, Lake County
Battery storage
300 MWIn study Lake, INMISO Mar 2022target 2024
Solar project J1743, Miami County
Solar
293 MWIn study Miami, INMISO Apr 2022target 2026
Solar project AI1-085, Wayne County
Solar
290 MWIn study Wayne, INPJM Jul 2022target 2030
Solar + storage project AH2-112, St. Joseph County
Solar + storage
250 MWIn study St. Joseph, INPJM Feb 2022target 2026
Solar project J2970, Posey County
Solar
250 MWIn study Posey, INMISO Sep 2022target 2026
Solar + storage project J3077, Gibson County
Solar + storage
250 MWIn study Gibson, INMISO Sep 2022target 2026
Battery storage project J2581, Ripley County
Battery storage
250 MWIn study Ripley, INMISO Sep 2022target 2026
Solar project J2849, Pulaski County
Solar
245 MWIn study Pulaski, INMISO Sep 2022target 2025
Solar + storage project AH2-419, Laporte County
Solar + storage
210 MWIn study Laporte, INPJM Mar 2022target 2026
Solar project J2566, Daviess County
Solar
200 MWIn study Daviess, INMISO Sep 2022target 2026
Battery storage project J2663, White County
Battery storage
200 MWIn study White, INMISO Sep 2022target 2026
Solar project J2230, Sullivan County
Solar
200 MWIn study Sullivan, INMISO Mar 2022target 2025
Battery storage project J2213, Marshall County
Battery storage
200 MWIn study Marshall, INMISO Mar 2022target 2028
Solar + storage project AI1-134, Grant County
Solar + storage
200 MWIn study Grant, INPJM Sep 2022target 2029
Solar + storage project J1642, Spencer County
Solar + storage
200 MWIn study Spencer, INMISO Feb 2022target 2023
Battery storage project J2472, Sullivan County
Battery storage
200 MWIn study Sullivan, INMISO Sep 2022target 2027
Battery storage project J2586, Clark County
Battery storage
200 MWIn study Clark, INMISO Sep 2022target 2025
Solar project J2987, Greene County
Solar
200 MWIn study Greene, INMISO Sep 2022target 2025
Battery storage project J2572, Hamilton County
Battery storage
200 MWIn study Hamilton, INMISO Sep 2022target 2025
Onshore wind project J2509, Tippecanoe County
Onshore wind
200 MWIn study Tippecanoe, INMISO Sep 2022target 2025
Battery storage project AH2-347, St. Joseph County
Battery storage
200 MWIn study St. Joseph, INPJM Mar 2022target 2025
Battery storage project J2280
Battery storage
198 MWIn study INMISO Mar 2022target 2023
Solar project J2353, White County
Solar
190 MWIn study White, INMISO Sep 2022target 2026
Solar + storage project AH2-153, Vermillion County
Solar + storage
180 MWIn study Vermillion, INPJM Feb 2022target 2024
Onshore wind project J2654, Clinton County
Onshore wind
180 MWIn study Clinton, INMISO Sep 2022target 2026
Solar project J2847, Starke County
Solar
180 MWIn study Starke, INMISO Sep 2022target 2026
Onshore wind project AI1-003, Huntington County
Onshore wind
170 MWIn study Huntington, INPJM Apr 2022target 2026
Solar project J2747, Greene County
Solar
160 MWIn study Greene, INMISO Sep 2022target 2026
Solar project J3145, Putnam County
Solar
150 MWIn study Putnam, INMISO Sep 2022target 2027
Solar project J3144, Putnam County
Solar
150 MWIn study Putnam, INMISO Sep 2022target 2027
Solar + storage project AH2-154, Vermillion County
Solar + storage
150 MWIn study Vermillion, INPJM Feb 2022target 2024
Battery storage project J2473, Marion County
Battery storage
150 MWIn study Marion, INMISO Sep 2022target 2026
Battery storage project J2657, White County
Battery storage
138 MWIn study White, INMISO Sep 2022target 2027
Solar project J2307, Miami County
Solar
130 MWIn study Miami, INMISO Mar 2022target 2025
Battery storage project J2343, Marion County
Battery storage
130 MWIn study Marion, INMISO Sep 2022target 2026
Solar + storage project AI1-080, Laporte County
Solar + storage
125 MWIn study Laporte, INPJM Jul 2022target 2026
Solar + storage project J2826, Greene County
Solar + storage
125 MWIn study Greene, INMISO Sep 2022target 2027
Solar project J2187, Laporte County
Solar
124 MWIn study Laporte, INMISO Mar 2022target 2024
Solar project J3168, White County
Solar
120 MWIn study White, INMISO Sep 2022target 2026
Solar project J2044, Newton County
Solar
100 MWIn study Newton, INMISO Mar 2022target 2024
Solar project J3207, Starke County
Solar
100 MWIn study Starke, INMISO Mar 2022target 2024
Page 1 of 2

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)