United States โบ Grid โบ Interconnection queues โบ Indiana
OCTARY USA ยท INTERCONNECTION QUEUESWithdrawn queue requests in Indiana
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Onshore wind project J236, White County Onshore wind |
2,400 MW | Withdrawn / abandoned |
| Onshore wind project X1-020, Cass County Onshore wind |
1,500 MW | Withdrawn / abandoned |
| Solar + storage project LGE-GIS-2022-005, Clarke County Solar + storage |
1,400 MW | Withdrawn / abandoned |
| Coal project G484, Switzerland County Coal |
1,290 MW | Withdrawn / abandoned |
| Gas project J802, Vermillion County Gas |
1,244 MW | Withdrawn / abandoned |
| Gas project J542, Vigo County Gas |
1,235 MW | Withdrawn / abandoned |
| Gas project J434, Vermillion County Gas |
1,185 MW | Withdrawn / abandoned |
| Gas project Y3-063, Lake County Gas |
1,161 MW | Withdrawn / abandoned |
| Gas project J259, Shelby County Gas |
1,065 MW | Withdrawn / abandoned |
| Solar + storage project LGE-GIS-2022-006, Clarke County Solar + storage |
1,000 MW | Withdrawn / abandoned |
| Gas project J250, Shelby County Gas |
999 MW | Withdrawn / abandoned |
| Gas project G011, Pike County Gas |
900 MW | Withdrawn / abandoned |
| Gas project J708, Posey County Gas |
847 MW | Withdrawn / abandoned |
| Gas project G015, Lawrence County Gas |
800 MW | Withdrawn / abandoned |
| Solar + storage project AE1-214, Spencer County Solar + storage |
800 MW | Withdrawn / abandoned |
| Solar + storage project AE2-130, Spencer County Solar + storage ยท Sand Ridge Solar Project LLC |
800 MW | Withdrawn / abandoned |
| Solar + storage project AF2-353, Spencer County Solar + storage |
800 MW | Withdrawn / abandoned |
| Gas project AH1-745, Vermillion County Gas ยท Tenaska Power Generation, LLC |
770 MW | Withdrawn / abandoned |
| Gas project AH1-740, Vermillion County Gas ยท Tenaska Power Generation, LLC |
770 MW | Withdrawn / abandoned |
| Gas project J240, Vermillion County Gas |
720 MW | Withdrawn / abandoned |
| Onshore wind project U4-039, Madison County Onshore wind |
710 MW | Withdrawn / abandoned |
| Gas project J215, St. Joseph County Gas |
670 MW | Withdrawn / abandoned |
| Gas project J1288, Vermillion County Gas |
667 MW | Withdrawn / abandoned |
| Coal project O65, St. Joseph County Coal |
650 MW | Withdrawn / abandoned |
| Other project G028, Jefferson County Other |
650 MW | Withdrawn / abandoned |
| Other project G027, Jefferson County Other |
650 MW | Withdrawn / abandoned |
| Other project G009, Vigo County Other |
640 MW | Withdrawn / abandoned |
| Coal project G039, Sullivan County Coal |
600 MW | Withdrawn / abandoned |
| Gas project J3215, Laporte County Gas |
594 MW | Withdrawn / abandoned |
| Gas project U1-058, St. Joseph County Gas |
586 MW | Withdrawn / abandoned |
| Coal project G758, Lake County Coal |
550 MW | Withdrawn / abandoned |
| Onshore wind project AD2-015, Benton County Onshore wind |
500 MW | Withdrawn / abandoned |
| Other project G029, Lawrence County Other |
500 MW | Withdrawn / abandoned |
| Solar + storage project AE1-216, White County Solar + storage |
500 MW | Withdrawn / abandoned |
| Other project G075, Putnam County Other |
500 MW | Withdrawn / abandoned |
| Onshore wind project V3-003, Clinton County Onshore wind |
500 MW | Withdrawn / abandoned |
| Battery storage project J2443, Kosciusko County Battery storage |
500 MW | Withdrawn / abandoned |
| Onshore wind project AD1-137, Benton County Onshore wind |
500 MW | Withdrawn / abandoned |
| Other project G030, Switzerland County Other |
500 MW | Withdrawn / abandoned |
| Onshore wind project AE1-197, White County Onshore wind |
500 MW | Withdrawn / abandoned |
| Onshore wind project G656, Benton County Onshore wind |
500 MW | Withdrawn / abandoned |
| Onshore wind project U1-024, Warren County Onshore wind |
500 MW | Withdrawn / abandoned |
| Solar + storage project AE1-215, White County Solar + storage |
500 MW | Withdrawn / abandoned |
| Onshore wind project G739, White County Onshore wind |
450 MW | Withdrawn / abandoned |
| Onshore wind project S31, White County Onshore wind |
450 MW | Withdrawn / abandoned |
| Battery storage project J3488, Vermillion County Battery storage |
400 MW | Withdrawn / abandoned |
| Solar project J3487, Vermillion County Solar |
400 MW | Withdrawn / abandoned |
| Onshore wind project X1-040, Dekalb County Onshore wind |
360 MW | Withdrawn / abandoned |
| Onshore wind project R61, Lagrange County Onshore wind |
350 MW | Withdrawn / abandoned |
| Solar + storage project J3119, Pulaski County Solar + storage |
350 MW | Withdrawn / abandoned |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
- MISO (Midcontinent)366 ยท 71.5 GW
- PJM (Mid-Atlantic, Midwest)210 ยท 40.3 GW
- Southeast (non-ISO utilities)3 ยท 2,600 MW
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)