United States โ€บ Grid โ€บ Interconnection queues โ€บ Indiana

OCTARY USA ยท INTERCONNECTION QUEUES

Withdrawn queue requests in Indiana

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown579114.4 GW
Active in queue59.6 GW300 requests
Agreement signed11.2 GW69 requests
Withdrawn579114.4 GW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

579 requests ยท page 1 of 12
ProjectCapacityStatusLocationRegionQueuedOnline
Onshore wind project J236, White County
Onshore wind
2,400 MWWithdrawn / abandoned White, INMISO Dec 2011target 2018
Onshore wind project X1-020, Cass County
Onshore wind
1,500 MWWithdrawn / abandoned Cass, INPJM Feb 2011target 2018
Solar + storage project LGE-GIS-2022-005, Clarke County
Solar + storage
1,400 MWWithdrawn / abandoned Clarke, INSoutheast Jul 2022target 2029
Coal project G484, Switzerland County
Coal
1,290 MWWithdrawn / abandoned Switzerland, INMISO Nov 2004target 2004
Gas project J802, Vermillion County
Gas
1,244 MWWithdrawn / abandoned Vermillion, INMISO Jun 2017target 2020
Gas project J542, Vigo County
Gas
1,235 MWWithdrawn / abandoned Vigo, INMISO Jan 2016target 2020
Gas project J434, Vermillion County
Gas
1,185 MWWithdrawn / abandoned Vermillion, INMISO Mar 2015target 2019
Gas project Y3-063, Lake County
Gas
1,161 MWWithdrawn / abandoned Lake, INPJM Mar 2013target 2018
Gas project J259, Shelby County
Gas
1,065 MWWithdrawn / abandoned Shelby, INMISO Nov 2012target 2015
Solar + storage project LGE-GIS-2022-006, Clarke County
Solar + storage
1,000 MWWithdrawn / abandoned Clarke, INSoutheast Aug 2022target 2029
Gas project J250, Shelby County
Gas
999 MWWithdrawn / abandoned Shelby, INMISO Aug 2012
Gas project G011, Pike County
Gas
900 MWWithdrawn / abandoned Pike, INMISO Oct 1999target 2002
Gas project J708, Posey County
Gas
847 MWWithdrawn / abandoned Posey, INMISO Sep 2016target 2019
Gas project G015, Lawrence County
Gas
800 MWWithdrawn / abandoned Lawrence, INMISO Nov 1999target 2003
Solar + storage project AE1-214, Spencer County
Solar + storage
800 MWWithdrawn / abandoned Spencer, INPJM Sep 2018target 2023
Solar + storage project AE2-130, Spencer County
Solar + storage ยท Sand Ridge Solar Project LLC
800 MWWithdrawn / abandoned Spencer, INPJM Feb 2019target 2022
Solar + storage project AF2-353, Spencer County
Solar + storage
800 MWWithdrawn / abandoned Spencer, INPJM Mar 2020target 2023
Gas project AH1-745, Vermillion County
Gas ยท Tenaska Power Generation, LLC
770 MWWithdrawn / abandoned Vermillion, INPJM target 2031
Gas project AH1-740, Vermillion County
Gas ยท Tenaska Power Generation, LLC
770 MWWithdrawn / abandoned Vermillion, INPJM target 2031
Gas project J240, Vermillion County
Gas
720 MWWithdrawn / abandoned Vermillion, INMISO Apr 2012target 2016
Onshore wind project U4-039, Madison County
Onshore wind
710 MWWithdrawn / abandoned Madison, INPJM Jan 2009target 2015
Gas project J215, St. Joseph County
Gas
670 MWWithdrawn / abandoned St. Joseph, INMISO Jun 2011target 2014
Gas project J1288, Vermillion County
Gas
667 MWWithdrawn / abandoned Vermillion, INMISO Apr 2019target 2023
Coal project O65, St. Joseph County
Coal
650 MWWithdrawn / abandoned St. Joseph, INPJM Jul 2005target 2010
Other project G028, Jefferson County
Other
650 MWWithdrawn / abandoned Jefferson, INMISO Jan 2000target 2000
Other project G027, Jefferson County
Other
650 MWWithdrawn / abandoned Jefferson, INMISO Jan 2000target 2002
Other project G009, Vigo County
Other
640 MWWithdrawn / abandoned Vigo, INMISO Jul 1999
Coal project G039, Sullivan County
Coal
600 MWWithdrawn / abandoned Sullivan, INMISO May 2000target 2003
Gas project J3215, Laporte County
Gas
594 MWWithdrawn / abandoned Laporte, INMISO Sep 2022target 2025
Gas project U1-058, St. Joseph County
Gas
586 MWWithdrawn / abandoned St. Joseph, INPJM Apr 2008target 2013
Coal project G758, Lake County
Coal
550 MWWithdrawn / abandoned Lake, INMISO Mar 2007target 2009
Onshore wind project AD2-015, Benton County
Onshore wind
500 MWWithdrawn / abandoned Benton, INPJM Nov 2017target 2020
Other project G029, Lawrence County
Other
500 MWWithdrawn / abandoned Lawrence, INMISO Jan 2000target 2002
Solar + storage project AE1-216, White County
Solar + storage
500 MWWithdrawn / abandoned White, INPJM Sep 2018target 2023
Other project G075, Putnam County
Other
500 MWWithdrawn / abandoned Putnam, INMISO Jan 2001target 2003
Onshore wind project V3-003, Clinton County
Onshore wind
500 MWWithdrawn / abandoned Clinton, INPJM Aug 2009target 2010
Battery storage project J2443, Kosciusko County
Battery storage
500 MWWithdrawn / abandoned Kosciusko, INMISO Sep 2022target 2025
Onshore wind project AD1-137, Benton County
Onshore wind
500 MWWithdrawn / abandoned Benton, INPJM Sep 2017target 2020
Other project G030, Switzerland County
Other
500 MWWithdrawn / abandoned Switzerland, INMISO Jan 2000target 2003
Onshore wind project AE1-197, White County
Onshore wind
500 MWWithdrawn / abandoned White, INPJM Sep 2018target 2021
Onshore wind project G656, Benton County
Onshore wind
500 MWWithdrawn / abandoned Benton, INMISO Jul 2006target 2006
Onshore wind project U1-024, Warren County
Onshore wind
500 MWWithdrawn / abandoned Warren, INPJM Feb 2008target 2010
Solar + storage project AE1-215, White County
Solar + storage
500 MWWithdrawn / abandoned White, INPJM Sep 2018target 2023
Onshore wind project G739, White County
Onshore wind
450 MWWithdrawn / abandoned White, INMISO Feb 2007target 2010
Onshore wind project S31, White County
Onshore wind
450 MWWithdrawn / abandoned White, INPJM May 2007target 2009
Battery storage project J3488, Vermillion County
Battery storage
400 MWWithdrawn / abandoned Vermillion, INMISO Apr 2024target 2028
Solar project J3487, Vermillion County
Solar
400 MWWithdrawn / abandoned Vermillion, INMISO Apr 2024target 2028
Onshore wind project X1-040, Dekalb County
Onshore wind
360 MWWithdrawn / abandoned Dekalb, INPJM Mar 2011target 2013
Onshore wind project R61, Lagrange County
Onshore wind
350 MWWithdrawn / abandoned Lagrange, INPJM Jan 2007target 2010
Solar + storage project J3119, Pulaski County
Solar + storage
350 MWWithdrawn / abandoned Pulaski, INMISO Sep 2022target 2026
Page 1 of 12

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)