United States β€Ί Grid β€Ί Interconnection queues β€Ί Indiana

ONSHORE WIND Β· MISO

Onshore wind project G656, Benton County

Onshore wind project G656, Benton County is a 500 MW onshore wind request withdrawn in the MISO interconnection queue, in Benton County, Indiana.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jul 2006 (completed)
  2. Withdrawn / abandonedMay 2009 (project stopped here)
  3. ConsentedMay 2009 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
G656
Grid region
MISO (Midcontinent)
Connection point (POI)
DEM Dequine - Westwood 345 kV
Location
Benton County, Indiana
Technology
Wind: 500 MW
Total requested
500 MW
Study phase
SPA - SIS
Queue status
Withdrawn
Entered queue
10 July 2006
Agreement signed
26 May 2009
Proposed online date
July 2006
Withdrawn
May 2009

Location

Marker shows the centre of Benton County; the queue data does not give exact sites.

Power plants in Indiana Β· Transmission lines in Indiana

Other requests in Benton County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem