United States β€Ί Grid β€Ί Interconnection queues β€Ί Indiana

ONSHORE WIND Β· MISO

Onshore wind project G739, White County

Onshore wind project G739, White County is a 450 MW onshore wind request withdrawn in the MISO interconnection queue, in White County, Indiana.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Feb 2007 (completed)
  2. Withdrawn / abandonedMar 2007 (project stopped here)
  3. ConsentedMar 2007 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
G739
Grid region
MISO (Midcontinent)
Connection point (POI)
Olive - Dequine 345 kV
Location
White County, Indiana
Technology
Wind: 450 MW
Total requested
450 MW
Queue status
Withdrawn
Entered queue
12 February 2007
Agreement signed
2 March 2007
Proposed online date
January 2010
Withdrawn
March 2007

Location

Marker shows the centre of White County; the queue data does not give exact sites.

Power plants in Indiana Β· Transmission lines in Indiana