Completed queue projects in Indiana

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown6911.3 GW
Active in queue59.6 GW300 requests
Agreement signed11.2 GW69 requests
Withdrawn579114.4 GW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

69 requests ยท page 1 of 2
ProjectCapacityStatusLocationRegionQueuedOnline
Gas project J238, Morgan County
Gas
725 MWOperating Morgan, INMISO Jan 20122018
St. Joseph Energy Center, LLC
Gas
675 MWOperating St. Joseph, INPJM Jun 20112018
Gas project G780, Vigo County
Gas
578 MWOperating Vigo, INMISO Apr 20072009
Gas project G010, Vigo County
Gas
500 MWOperating Vigo, INMISO Aug 19992007
Fowler Ridge WF
Onshore wind
500 MWOperating Benton, INPJM Feb 20062008
Coal project J089, Warrick County
Coal
447 MWOperating Warrick, INMISO Oct 20092012
Gas project G431, Knox County
Gas
420 MWOperating Knox, INMISO Jun 20042007
Onshore wind project J515, Benton County
Onshore wind
400 MWOperating Benton, INMISO Nov 20152019
Gas project G084, Lawrence County
Gas
320 MWOperating Lawrence, INMISO Mar 20012005
Mammoth North Solar Project
Solar
300 MWOperating Starke, INPJM Sep 20192024
Solar project J1295, Gibson County
Solar
280 MWOperating Gibson, INMISO Apr 20192023
Fowler Ridge 4 WF
Onshore wind
250 MWOperating Benton, INPJM Feb 20062015
Gas project G064, Hamilton County
Gas
210 MWOperating Hamilton, INMISO Oct 20002005
Meadow Lake
Onshore wind
202 MWOperating White, INPJM Feb 20072009
Onshore wind project J838, White County
Onshore wind
200 MWOperating White, INMISO Jun 20172021
Onshore wind project J837, White County
Onshore wind
200 MWOperating White, INMISO Jun 20172021
Wildcat Wind Farm I
Onshore wind
200 MWOperating Madison, INPJM Aug 20082012
Meadow Lake WF 4 - 5
Onshore wind
200 MWOperating White, INPJM Jan 20082010
Meadow Lake WF II, Meadow Lake WF III
Onshore wind
200 MWOperating Benton, INPJM Jan 20082010
Coal project G675, Knox County
Coal
200 MWOperating Knox, INMISO Aug 20062008
Meadow Lake Wind Farm VI
Onshore wind
200 MWOperating White, INPJM May 20152018
Onshore wind project J968, Jasper County
Onshore wind
200 MWOperating Jasper, INMISO Mar 20182023
HeadwatersWF
Onshore wind
200 MWOperating Randolph, INPJM Jul 20082014
Headwaters II
Onshore wind
200 MWOperating Randolph, INPJM Aug 20092021
Solar project J913, White County
Solar
200 MWOperating White, INMISO Jun 20172022
Solar + storage project J1335, Jasper County
Solar + storage
200 MWOperating Jasper, INMISO Apr 20192024
Solar + storage project J1334, Jasper County
Solar + storage
200 MWOperating Jasper, INMISO Apr 20192024
Solar + storage project J1333, Jasper County
Solar + storage
200 MWOperating Jasper, INMISO Apr 20192024
Gas project G025, Marion County
Gas
189 MWOperating Marion, INMISO Jan 20002007
Coal project J334, Vigo County
Coal
180 MWOperating Vigo, INMISO May 20142010
Coal project J333, Vigo County
Coal
170 MWOperating Vigo, INMISO May 20142010
Bellflower Solar 1
Solar
153 MWOperating Henry, INPJM Mar 20192022
Solar project J1396, Pike County
Solar
150 MWOperating Pike, INMISO Apr 20192024
Honeysuckle Solar Project
Solar
150 MWOperating St. Joseph, INPJM Sep 20192025
Bitter Ridge Wind Farm
Onshore wind
130 MWOperating Jay, INPJM Mar 20172020
Bluff Point
Onshore wind
120 MWOperating Jay, INPJM Jul 20072017
Onshore wind project J513, White County
Onshore wind
100 MWOperating White, INMISO Nov 20152020
Riverstart Solar Park
Solar
100 MWOperating Randolph, INPJM Oct 20162021
Onshore wind project J431, Benton County
Onshore wind
100 MWOperating Benton, INMISO Dec 20142017
Mammoth North Solar Project
Solar
100 MWOperating Starke, INPJM Mar 20202024
Onshore wind project N001, Benton County
Onshore wind
100 MWOperating Benton, INMISO Jan 20032008
Riverstart Solar Park III
Solar
100 MWOperating Randolph, INPJM Mar 20172024
Onshore wind project G439, Benton County
Onshore wind
100 MWOperating Benton, INMISO Jul 20042005
Riverstart Solar Park
Solar
100 MWOperating Randolph, INPJM Oct 20162021
Hydro project G849, Perry County
Hydro
84.0 MWOperating Perry, INMISO Sep 20072016
Coal project G674, Knox County
Coal
80.0 MWOperating Knox, INMISO Aug 20062008
Solar project J759, Spencer County
Solar
70.0 MWOperating Spencer, INMISO Nov 20162020
Lawrenceburg Generating Plant
Gas
50.0 MWOperating Dearborn, INPJM Oct 20162019
Lawrenceburg Generating Plant
Gas
50.0 MWOperating Dearborn, INPJM Oct 20162019
St. Joseph's Energy Center, LLC
Gas
40.0 MWOperating St. Joseph, INPJM Sep 20152018
Page 1 of 2

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)