🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Florida

OCTARY USA · INTERCONNECTION QUEUES

Solar interconnection queue in Florida

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown21715.9 GW
Active in queue15.9 GW217 requests
Agreement signed107 MW3 requests
Withdrawn33023.5 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

217 requests · page 1 of 5
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project 344, Madison County
Solar · Duke Energy Florida, LLC
74.9 MWUnder construction Madison, FLSoutheast Jan 2024target 2026
Solar project 259, Highlands County
Solar · Placid Solar II, LLC
74.9 MWUnder construction Highlands, FLSoutheast May 2019target 2023
Solar project 218, Suwannee County
Solar · Twin Rivers Solar, LLC
74.9 MWIn study Suwannee, FLSoutheast Feb 2018target 2020
Solar project 605, Desoto County
Solar · FPL
74.9 MWIn study Desoto, FLSoutheast Dec 2023target 2032
Solar project FC100384, Suwannee County
Solar · Duke Energy Florida, LLC
74.9 MWIn study Suwannee, FLSoutheast Dec 2025target 2030
Solar project 343, Orange County
Solar · Duke Energy Florida, LLC
74.9 MWUnder construction Orange, FLSoutheast Jan 2024target 2028
Solar project FC100007, Madison County
Solar · Duke Energy Florida, LLC
74.9 MWIn study Madison, FLSoutheast Nov 2024target 2028
Solar project 326, Osceola County
Solar · Duke Energy Florida, LLC
74.9 MWUnder construction Osceola, FLSoutheast May 2023target 2027
Solar project 604, Desoto County
Solar · FPL
74.9 MWIn study Desoto, FLSoutheast Dec 2023target 2032
Solar project FC100018, Liberty County
Solar · Duke Energy Florida, LLC
74.9 MWIn study Liberty, FLSoutheast Dec 2024target 2028
Solar project 307, Suwannee County
Solar · CP Ironwood, LLC
74.9 MWPaused / redesign Suwannee, FLSoutheast Apr 2022target 2026
Solar project 342, Orange County
Solar · Duke Energy Florida, LLC
74.9 MWUnder construction Orange, FLSoutheast Jan 2024target 2027
Solar project 258, Highlands County
Solar · Placid Solar, LLC
74.9 MWUnder construction Highlands, FLSoutheast May 2019target 2023
Solar project FC100012, Hamilton County
Solar · Duke Energy Florida, LLC
74.9 MWIn study Hamilton, FLSoutheast Nov 2024target 2028
Solar project 323, Jackson County
Solar · Duke Energy Florida, LLC
74.9 MWUnder construction Jackson, FLSoutheast Feb 2023target 2027
Solar project 202.1, Levy County
Solar · FL SB 9, LLC
74.9 MWUnder construction Levy, FLSoutheast Oct 2017target 2021
Solar project 610, Charlotte County
Solar · FPL
74.9 MWIn study Charlotte, FLSoutheast Dec 2023target 2032
Solar project 319, Hernando County
Solar · Duke Energy Florida, LLC
74.9 MWPaused / redesign Hernando, FLSoutheast Dec 2022target 2026
Solar project FC100004, Sumter County
Solar · Duke Energy Florida, LLC
74.9 MWIn study Sumter, FLSoutheast Nov 2024target 2028
Solar project 273, Polk County
Solar · FL Solar 10, LLC
74.9 MWUnder construction Polk, FLSoutheast Dec 2019target 2022
Solar project 607, Charlotte County
Solar · FPL
74.9 MWIn study Charlotte, FLSoutheast Dec 2023target 2032
Solar project 608, Charlotte County
Solar · FPL
74.9 MWIn study Charlotte, FLSoutheast Dec 2023target 2032
Solar project 612, Charlotte County
Solar · FPL
74.9 MWIn study Charlotte, FLSoutheast Dec 2023target 2032
Solar project 290, Suwannee County
Solar · Echo River Solar Project, LLC
74.9 MWIn study Suwannee, FLSoutheast Dec 2020target 2025
Solar project 322, Sumter County
Solar · Duke Energy Florida, LLC
74.9 MWUnder construction Sumter, FLSoutheast Dec 2022target 2026
Solar project 341, Orange County
Solar · Duke Energy Florida, LLC
74.9 MWUnder construction Orange, FLSoutheast Jan 2024target 2026
Solar project 611, Charlotte County
Solar · FPL
74.9 MWIn study Charlotte, FLSoutheast Dec 2023target 2032
Solar project FC100383, Liberty County
Solar · Duke Energy Florida, LLC
74.9 MWIn study Liberty, FLSoutheast Dec 2025target 2029
Solar project 269, Marion County
Solar · Solar FL 2018 LLC
74.9 MWIn study Marion, FLSoutheast Sep 2019target 2021
Solar project 320, Hernando County
Solar · Duke Energy Florida, LLC
74.9 MWPaused / redesign Hernando, FLSoutheast Dec 2022target 2027
Solar project 305, Suwannee County
Solar · CP Ironwood, LLC
74.9 MWPaused / redesign Suwannee, FLSoutheast Apr 2022target 2026
Solar project 609, Charlotte County
Solar · FPL
74.9 MWIn study Charlotte, FLSoutheast Dec 2023target 2032
Solar project 293, Alachua County
Solar · Pleasant Solar, LLC
74.9 MWPaused / redesign Alachua, FLSoutheast Aug 2021target 2024
Solar project 338, Hamilton County
Solar · Duke Energy Florida, LLC
74.9 MWPaused / redesign Hamilton, FLSoutheast Nov 2023target 2025
Solar project FC100006, Madison County
Solar · Duke Energy Florida, LLC
74.9 MWIn study Madison, FLSoutheast Nov 2024target 2028
Solar project 308, Suwannee County
Solar · CP Ironwood, LLC
74.9 MWPaused / redesign Suwannee, FLSoutheast Apr 2022target 2026
Solar project FC100385, Suwannee County
Solar · Duke Energy Florida, LLC
74.9 MWIn study Suwannee, FLSoutheast Dec 2025target 2030
Solar project 325, Osceola County
Solar · Duke Energy Florida, LLC
74.9 MWUnder construction Osceola, FLSoutheast May 2023target 2026
Solar project 503, Martin County
Solar · FPL
74.5 MWIn study Martin, FLSoutheast Jan 2023target 2030
Solar project 507, Martin County
Solar · FPL
74.5 MWIn study Martin, FLSoutheast Jan 2023target 2030
Solar project 534, Hendry County
Solar · FPL
74.5 MWIn study Hendry, FLSoutheast Jan 2023target 2031
Solar project 497, Martin County
Solar · FPL
74.5 MWIn study Martin, FLSoutheast Jan 2023target 2029
Solar project 551, Hendry County
Solar · FPL
74.5 MWIn study Hendry, FLSoutheast Jan 2023target 2032
Solar project 511, Manatee County
Solar · FPL
74.5 MWIn study Manatee, FLSoutheast Jan 2023target 2031
Storey Bend South
Solar
74.5 MWIn study Osceola, FLSoutheast Feb 2024target 2026
Solar project 542, Hendry County
Solar · FPL
74.5 MWIn study Hendry, FLSoutheast Jan 2023target 2031
Solar project 171, Gilchrist County
Solar · Florida Renewable Partners, LLC
74.5 MWIn study Gilchrist, FLSoutheast Dec 2016target 2021
Solar project 504, Martin County
Solar · FPL
74.5 MWIn study Martin, FLSoutheast Jan 2023target 2030
Solar project 517, Charlotte County
Solar · FPL
74.5 MWIn study Charlotte, FLSoutheast Jan 2023target 2030
Solar project 519, Charlotte County
Solar · FPL
74.5 MWIn study Charlotte, FLSoutheast Jan 2023target 2031
Page 1 of 5

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)