United States โบ Grid โบ Interconnection queues โบ Arizona
OCTARY USA ยท INTERCONNECTION QUEUESWithdrawn queue requests in Arizona (2021 requests)
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Battery storage project Q400, Coconino County Battery storage |
1,700 MW | Withdrawn / abandoned |
| Hyder Solar + storage |
1,648 MW | Withdrawn / abandoned |
| Onshore wind project Q75, Apache County Onshore wind |
1,500 MW | Withdrawn / abandoned |
| Other project Q82, Apache County Other |
1,300 MW | Withdrawn / abandoned |
| Solar + storage project 94, Pima County Solar + storage |
1,110 MW | Withdrawn / abandoned |
| La Paz 2 Solar + storage |
1,034 MW | Withdrawn / abandoned |
| Adobe Flats Solar + storage |
1,024 MW | Withdrawn / abandoned |
| Solar + storage project 105, Greenlee County Solar + storage |
1,000 MW | Withdrawn / abandoned |
| Onshore wind project Q74, Apache County Onshore wind |
1,000 MW | Withdrawn / abandoned |
| Solar project 104, Apache County Solar |
1,000 MW | Withdrawn / abandoned |
| Primrose Hybrid Solar + storage |
912 MW | Withdrawn / abandoned |
| Solar + storage project Q77, Navajo County Solar + storage |
908 MW | Withdrawn / abandoned |
| Solar + storage project Q68, Navajo County Solar + storage |
900 MW | Withdrawn / abandoned |
| Solar + storage project Q21, Maricopa County Solar + storage |
864 MW | Withdrawn / abandoned |
| Solar + storage project Q396, Navajo County Solar + storage |
850 MW | Withdrawn / abandoned |
| Solar + storage project Q414, Yuma County Solar + storage |
800 MW | Withdrawn / abandoned |
| Solar + storage project Q403, Navajo County Solar + storage |
750 MW | Withdrawn / abandoned |
| Solar + storage project Q01, Maricopa County Solar + storage |
720 MW | Withdrawn / abandoned |
| Other project Q433, Coconino County Other |
700 MW | Withdrawn / abandoned |
| Solar + storage project Q80, Apache County Solar + storage |
643 MW | Withdrawn / abandoned |
| Solar + storage project Q87, Maricopa County Solar + storage |
630 MW | Withdrawn / abandoned |
| Solar + storage project Q20, Pinal County Solar + storage |
607 MW | Withdrawn / abandoned |
| Solar + storage project Q19, Pinal County Solar + storage |
600 MW | Withdrawn / abandoned |
| Onshore wind project Q73, Apache County Onshore wind |
500 MW | Withdrawn / abandoned |
| Solar + storage project Q428, Navajo County Solar + storage |
500 MW | Withdrawn / abandoned |
| Solar + storage project Q417, Coconino County Solar + storage |
500 MW | Withdrawn / abandoned |
| Solar + storage project Q79, Pinal County Solar + storage |
500 MW | Withdrawn / abandoned |
| Onshore wind project Q418, Coconino County Onshore wind |
500 MW | Withdrawn / abandoned |
| Solar + storage project Q430, Coconino County Solar + storage |
500 MW | Withdrawn / abandoned |
| Solar + storage project Q416, Pinal County Solar + storage |
500 MW | Withdrawn / abandoned |
| Battery storage project Q84, Maricopa County Battery storage |
463 MW | Withdrawn / abandoned |
| Winged Dove Storage Battery storage |
409 MW | Withdrawn / abandoned |
| Onshore wind project Q86, Navajo County Onshore wind |
407 MW | Withdrawn / abandoned |
| Solar + storage project Q88, Pinal County Solar + storage |
405 MW | Withdrawn / abandoned |
| Solar + storage project Q17, Pinal County Solar + storage |
400 MW | Withdrawn / abandoned |
| Battery storage project Q406, Yuma County Battery storage |
400 MW | Withdrawn / abandoned |
| Solar + storage project Q69, Pinal County Solar + storage |
400 MW | Withdrawn / abandoned |
| Solar + storage project Q369, San Juan County Solar + storage |
400 MW | Withdrawn / abandoned |
| Solar + storage project Q02, Maricopa County Solar + storage |
400 MW | Withdrawn / abandoned |
| Onshore wind project Q366, Coconino County Onshore wind |
400 MW | Withdrawn / abandoned |
| Solar + storage project Q18, Pinal County Solar + storage |
400 MW | Withdrawn / abandoned |
| Battery storage project Q436, Coconino County Battery storage |
400 MW | Withdrawn / abandoned |
| Onshore wind project 97, Apache County Onshore wind |
400 MW | Withdrawn / abandoned |
| Brenda Renewable Energy Complex Solar |
358 MW | Withdrawn / abandoned |
| Battery storage project 99, Pinal County Battery storage |
319 MW | Withdrawn / abandoned |
| Battery storage project Q399, Coconino County Battery storage |
300 MW | Withdrawn / abandoned |
| Onshore wind project Q381, Pinal County Onshore wind |
300 MW | Withdrawn / abandoned |
| Solar + storage project Q371, Yuma County Solar + storage |
300 MW | Withdrawn / abandoned |
| Solar + storage project Q385, Pinal County Solar + storage |
300 MW | Withdrawn / abandoned |
| Solar + storage project Q426, Pinal County Solar + storage |
250 MW | Withdrawn / abandoned |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)