United States βΊ Grid βΊ Interconnection queues βΊ Arizona
SOLAR + STORAGE Β· WESTSolar + storage project Q396, Navajo County
Solar + storage project Q396, Navajo County is a 850 MW solar + storage request withdrawn in the West interconnection queue, in Navajo County, Arizona, connecting to Arizona Public Service.
Queue statusWithdrawn / abandoned
- PlanningQueued Sep 2021 (completed)
- Withdrawn / abandoned (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- Q396
- Grid region
- West (non-ISO utilities)
- Utility / transmission owner
- Arizona Public Service
- Connection point (POI)
- 345 kV Interconnection into both Four Corners - Cholla 345 kV lines abot 10 miles from the Cholla Substation
- Location
- Navajo County, Arizona
- Technology
- Solar: 850 MW Β· Battery
- Total requested
- 850 MW
- Service type
- NRIS and ERIS
- Study phase
- Withdrawn
- Queue status
- Withdrawn
- Entered queue
- 15 September 2021
- Proposed online date
- June 2024
Location
Marker shows the centre of Navajo County; the queue data does not give exact sites.
Other requests in Navajo County
- Solar + storage project Q270, Navajo CountySolar + storage Β· 200 MW Β· under construction
- Solar project Q230, Navajo CountySolar Β· 200 MW Β· under construction
- Battery storage project Q271, Navajo CountyBattery storage Β· 75.0 MW Β· under construction
- Solar + storage project Q275, Navajo CountySolar + storage Β· 1,000 MW Β· agreement signed
- Solar + storage project Q2409, Navajo CountySolar + storage Β· 2,626 MW Β· in study
- Solar + storage project Q2412, Navajo CountySolar + storage Β· 822 MW Β· in study
- Solar + storage project Q402, Navajo CountySolar + storage Β· 750 MW Β· in study
- Solar + storage project Q387, Navajo CountySolar + storage Β· 588 MW Β· in study
- Wind + storage project Q311, Navajo CountyWind + storage Β· 500 MW Β· in study
- Solar + storage project Q528, Navajo CountySolar + storage Β· 500 MW Β· in study
- Other project Q609, Navajo CountyOther Β· 500 MW Β· in study
- Onshore wind project Q273, Navajo CountyOnshore wind Β· 477 MW Β· in study
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem