Solar + storage project Q396, Navajo County

Solar + storage project Q396, Navajo County is a 850 MW solar + storage request withdrawn in the West interconnection queue, in Navajo County, Arizona, connecting to Arizona Public Service.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Sep 2021 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
Q396
Grid region
West (non-ISO utilities)
Utility / transmission owner
Arizona Public Service
Connection point (POI)
345 kV Interconnection into both Four Corners - Cholla 345 kV lines abot 10 miles from the Cholla Substation
Location
Navajo County, Arizona
Technology
Solar: 850 MW Β· Battery
Total requested
850 MW
Service type
NRIS and ERIS
Study phase
Withdrawn
Queue status
Withdrawn
Entered queue
15 September 2021
Proposed online date
June 2024

Location

Marker shows the centre of Navajo County; the queue data does not give exact sites.