Winged Dove Storage

Winged Dove Storage is a 409 MW battery storage request withdrawn in the CAISO interconnection queue, in Yuma County, Arizona, connecting to SDGE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2021 (completed)
  2. Withdrawn / abandonedJan 2023 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
2175
Grid region
CAISO (California)
Utility / transmission owner
SDGE
Connection point (POI)
Hoodoo Wash Switchyard 500 kV
Location
Yuma County, Arizona
Technology
Battery: 409 MW
Total requested
409 MW
Service type
Network resource (NRIS)
Study phase
System Impact Study
Queue status
Withdrawn
Entered queue
15 April 2021
Proposed online date
March 2028
Withdrawn
January 2023

Location

Marker shows the centre of Yuma County; the queue data does not give exact sites.