πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Arizona

SOLAR + STORAGE Β· WEST

Solar + storage project Q369, San Juan County

Solar + storage project Q369, San Juan County is a 400 MW solar + storage request withdrawn in the West interconnection queue, in San Juan County, Arizona, connecting to Arizona Public Service.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2021 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
Q369
Grid region
West (non-ISO utilities)
Utility / transmission owner
Arizona Public Service
Connection point (POI)
FourCorners 345 kV
Location
San Juan County, Arizona
Technology
Solar: 400 MW Β· Battery
Total requested
400 MW
Service type
Network resource (NRIS)
Study phase
Withdrawn
Queue status
Withdrawn
Entered queue
23 March 2021
Proposed online date
June 2024

Location

Marker shows the centre of San Juan County; the queue data does not give exact sites.

Power plants in Arizona Β· Transmission lines in Arizona

Other requests in San Juan County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem