United States β€Ί Grid β€Ί Interconnection queues

OCTARY USA Β· INTERCONNECTION QUEUES

Withdrawn queue requests in West (non-ISO utilities) (2011 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown15712.8 GW
Active in queue3,131 MW11 requests
Agreement signed1,563 MW5 requests
Withdrawn15712.8 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

157 requests Β· page 1 of 4
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project Q17, Maricopa County
Solar
700 MWWithdrawn / abandoned Maricopa, AZWest Apr 2011target 2014
Gas project 403, Sevier County
Gas
525 MWWithdrawn / abandoned Sevier, UTWest Oct 2011target 2014
Onshore wind project G0462, Lake County
Onshore wind
500 MWWithdrawn / abandoned Lake, ORWest Sep 2011target 2014
Coal project GI-1106, Pennington County
Coal
500 MWWithdrawn / abandoned Pennington, SDWest Nov 2011target 2019
Solar project Q193, Maricopa County
Solar
450 MWWithdrawn / abandoned Maricopa, AZWest Mar 2011target 2015
Gas project G0452, Umatilla County
Gas
410 MWWithdrawn / abandoned Umatilla, ORWest May 2011target 2015
Onshore wind project G0463, Lake County
Onshore wind
400 MWWithdrawn / abandoned Lake, ORWest Sep 2011target 2014
EPE Gen - Caliente
Gas
348 MWWithdrawn / abandoned El Paso, TXWest Feb 2011target 2015
EPE Gen - Megellan
Gas
348 MWWithdrawn / abandoned El Paso, TXWest Jan 2011target 2015
Gas project 36, Snohomish County
Gas
323 MWWithdrawn / abandoned Snohomish, WAWest Nov 2011target 2015
Other project Q197, Coconino County
Other
302 MWWithdrawn / abandoned Coconino, AZWest May 2011target 2013
Solar project Q184, Maricopa County
Solar
300 MWWithdrawn / abandoned Maricopa, AZWest Jan 2011target 2017
Solar project Q16, Maricopa County
Solar
300 MWWithdrawn / abandoned Maricopa, AZWest Apr 2011target 2014
Onshore wind project 398-B, Bonneville County
Onshore wind
288 MWWithdrawn / abandoned Bonneville, IDWest Aug 2011target 2012
Gas project 377, Salt Lake County
Gas
275 MWWithdrawn / abandoned Salt Lake, UTWest Mar 2011target 2014
Onshore wind project Q203, Coconino County
Onshore wind
250 MWWithdrawn / abandoned Coconino, AZWest Jul 2011target 2014
Onshore wind project 33, Adams County
Onshore wind
250 MWWithdrawn / abandoned Adams, WAWest Feb 2011target 2017
Onshore wind project Q23, San Bernardino County
Onshore wind
243 MWWithdrawn / abandoned San Bernardino, CAWest Nov 2011target 2017
Gas project 30, Skagit County
Gas
232 MWWithdrawn / abandoned Skagit, WAWest Feb 2011target 2014
Onshore wind project 375, Carbon County
Onshore wind
230 MWWithdrawn / abandoned Carbon, WYWest Mar 2011target 2014
Gas project G0460, Umatilla County
Gas
220 MWWithdrawn / abandoned Umatilla, ORWest Aug 2011target 2015
Onshore wind project Q22, San Bernardino County
Onshore wind
200 MWWithdrawn / abandoned San Bernardino, CAWest Nov 2011target 2016
Solar project Q178, San Juan County
Solar
200 MWWithdrawn / abandoned San Juan, NMWest Jan 2011target 2015
Other project Company FK, White Pine County
Other
200 MWWithdrawn / abandoned White Pine, NVWest Apr 2011target 2015
Onshore wind project 145, Stillwater County
Onshore wind
200 MWWithdrawn / abandoned Stillwater, MTWest Jul 2011target 2013
Onshore wind project GI-1104, Pennington County
Onshore wind
200 MWWithdrawn / abandoned Pennington, SDWest Sep 2011target 2010
Onshore wind project 147, Stillwater County
Onshore wind
200 MWWithdrawn / abandoned Stillwater, MTWest Aug 2011target 2013
Onshore wind project 398-A, Bonneville County
Onshore wind
192 MWWithdrawn / abandoned Bonneville, IDWest Aug 2011target 2012
Onshore wind project 32, Kittitas County
Onshore wind
176 MWWithdrawn / abandoned Kittitas, WAWest Apr 2011target 2014
Solar project Company 110, Clark County
Solar
150 MWWithdrawn / abandoned Clark, NVWest Jul 2011target 2015
Onshore wind project 31, Whitman County
Onshore wind
150 MWWithdrawn / abandoned Whitman, WAWest Feb 2011target 2014
Solar project Q201, Maricopa County
Solar
150 MWWithdrawn / abandoned Maricopa, AZWest Jun 2011target 2014
Solar project Company 113, Clark County
Solar
150 MWWithdrawn / abandoned Clark, NVWest Nov 2011target 2015
Solar project Q20, Inyo County
Solar
138 MWWithdrawn / abandoned Inyo, CAWest Oct 2011target 2014
Onshore wind project G0467, Wasco County
Onshore wind
101 MWWithdrawn / abandoned Wasco, ORWest Oct 2011target 2015
Solar project 369, Iron County
Solar
100 MWWithdrawn / abandoned Iron, UTWest Feb 2011target 2013
Solar project Q183, San Juan County
Solar
100 MWWithdrawn / abandoned San Juan, NMWest Jan 2011target 2014
Solar project Q179, San Juan County
Solar
100 MWWithdrawn / abandoned San Juan, NMWest Jan 2011target 2014
Solar project Company 102, Clark County
Solar
100 MWWithdrawn / abandoned Clark, NVWest Jan 2011target 2014
Onshore wind project 32, Whitman County
Onshore wind
100 MWWithdrawn / abandoned Whitman, WAWest Feb 2011target 2012
Gas project CLPT-G3, Laramie County
Gas
100 MWWithdrawn / abandoned Laramie, WYWest Jul 2011target 2014
Solar project Q180, San Juan County
Solar
100 MWWithdrawn / abandoned San Juan, NMWest Jan 2011target 2015
Onshore wind project 402, Albany County
Onshore wind
92.0 MWWithdrawn / abandoned Albany, WYWest Oct 2011target 2018
Onshore wind project GI-1102, Blaine County
Onshore wind
90.0 MWWithdrawn / abandoned Blaine, MTWest Feb 2011target 2013
Onshore wind project Company 105, Clark County
Onshore wind
85.5 MWWithdrawn / abandoned Clark, NVWest Feb 2011target 2015
Onshore wind project 379, Morrow / Umatilla County
Onshore wind
80.0 MWWithdrawn / abandoned Morrow / Umatilla, ORWest Mar 2011target 2012
Onshore wind project 400, San Juan County
Onshore wind Β· PacifiCorp Energy
80.0 MWWithdrawn / abandoned San Juan, UTWest Sep 2011target 2013
Onshore wind project 378, Morrow / Umatilla County
Onshore wind
80.0 MWWithdrawn / abandoned Morrow / Umatilla, ORWest Mar 2011target 2012
Gas project G0459, Linn County
Gas
65.0 MWWithdrawn / abandoned Linn, ORWest Aug 2011target 2013
Solar project 388, Jerome County
Solar
60.0 MWWithdrawn / abandoned Jerome, IDWest Dec 2011
Page 1 of 4

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)