πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Washington

ONSHORE WIND Β· WEST

Onshore wind project 33, Adams County

Onshore wind project 33, Adams County is a 250 MW onshore wind request withdrawn in the West interconnection queue, in Adams County, Washington, connecting to Avista Utilities.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Feb 2011 (completed)
  2. Withdrawn / abandonedOct 2013 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
33
Grid region
West (non-ISO utilities)
Utility / transmission owner
Avista Utilities
Connection point (POI)
A 115 kV interconnection Near Lind 115 kV Substation
Location
Adams County, Washington
Technology
Wind: 250 MW
Total requested
250 MW
Service type
NRIS and ERIS
Queue status
Withdrawn
Entered queue
18 February 2011
Proposed online date
November 2017
Withdrawn
October 2013

Location

Marker shows the centre of Adams County; the queue data does not give exact sites.

Power plants in Washington Β· Transmission lines in Washington

Other requests in Adams County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem