πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Washington

ONSHORE WIND Β· WEST

Onshore wind project 32, Kittitas County

Onshore wind project 32, Kittitas County is a 176 MW onshore wind request withdrawn in the West interconnection queue, in Kittitas County, Washington, connecting to Puget Sound Energy.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2011 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
32
Grid region
West (non-ISO utilities)
Utility / transmission owner
Puget Sound Energy
Connection point (POI)
Cascade-Rocky Reach 230 kV Line
Location
Kittitas County, Washington
Technology
Wind: 176 MW
Total requested
176 MW
Service type
NRIS and ERIS
Study phase
Withdrawn
Queue status
Withdrawn
Entered queue
20 April 2011
Proposed online date
September 2014

Location

Marker shows the centre of Kittitas County; the queue data does not give exact sites.

Power plants in Washington Β· Transmission lines in Washington

Other requests in Kittitas County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem