United States › Grid › Interconnection queues › Washington

SOLAR · WEST

Solar project 51, Kittitas County

Solar project 51, Kittitas County is a 79.2 MW solar request suspended in the West interconnection queue, in Kittitas County, Washington, connecting to Puget Sound Energy.

Queue statusPaused / redesign
  1. PlanningQueued Sep 2017 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2028 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
51
Grid region
West (non-ISO utilities)
Utility / transmission owner
Puget Sound Energy
Connection point (POI)
Cascade - Rocky Reach 230kV Line
Location
Kittitas County, Washington
Technology
Solar: 79.2 MW
Total requested
79.2 MW
Service type
Energy only (ERIS)
Study phase
Suspended LGIA
Queue status
Suspended
Entered queue
13 September 2017
Proposed online date
December 2028

Location

Marker shows the centre of Kittitas County; the queue data does not give exact sites.

Power plants in Washington · Transmission lines in Washington

Other requests in Kittitas County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem