ONSHORE WIND · WESTHorizon Wind Energy-WRidge
Horizon Wind Energy-WRidge is a 252 MW onshore wind request withdrawn in the West interconnection queue, in Kittitas County, Washington, connecting to Wind Ridge Power Partners, LLC.
Queue statusWithdrawn / abandoned
- PlanningQueued Jan 2003 (completed)
- Withdrawn / abandoned (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- G114
- Grid region
- West (non-ISO utilities)
- Utility / transmission owner
- Wind Ridge Power Partners, LLC
- Developer
- Wind Ridge Power Partners, LLC
- Connection point (POI)
- 230 kV Columbia - Covington line near Kittitas
- Location
- Kittitas County, Washington
- Technology
- Wind: 252 MW
- Total requested
- 252 MW
- Service type
- Energy only (ERIS)
- Queue status
- Withdrawn
- Entered queue
- 23 January 2003
- Proposed online date
- September 2004
Location
Marker shows the centre of Kittitas County; the queue data does not give exact sites.
Power plants in Washington · Transmission lines in Washington
Other requests in Kittitas County
- Onshore wind project 13, Kittitas CountyOnshore wind · 104 MW · agreement signed
- Solar project 49, Kittitas CountySolar · 100 MW · agreement signed
- Onshore wind project 1 Pre Jan 2004, Kittitas CountyOnshore wind · 200 MW · in study
- Solar + storage project C1-37, Kittitas CountySolar + storage · 199 MW · suspended
- Solar project 51, Kittitas CountySolar · 79.2 MW · suspended
- Kittitas Valley WindOnshore wind · 108 MW · built
- Onshore wind project 5, Kittitas CountyOnshore wind · 65.0 MW · built
- Onshore wind project 2, Kittitas CountyOnshore wind · 40.0 MW · built
- Onshore wind project 17, Kittitas CountyOnshore wind · 12.0 MW · built
- Onshore wind project G1034, Kittitas CountyOnshore wind · 400 MW · withdrawn
- Onshore wind project G1026, Kittitas CountyOnshore wind · 316 MW · withdrawn
- Solar + storage project 116, Kittitas CountySolar + storage · 300 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem