Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown23250.1 GW
Active in queue50.1 GW232 requests
Agreement signed13.3 GW77 requests
Withdrawn45299.2 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

232 requests Β· page 1 of 5
ProjectCapacityStatusLocationRegionQueuedOnline
Gas project GEN-2024-340, Creek County
Gas
1,400 MWIn study Creek, OKSPP Mar 2025target 2032
Gas project GEN-2024-132, Johnston County
Gas
1,300 MWIn study Johnston, OKSPP Mar 2025target 2031
Gas project GEN-2024-341, Pittsburg County
Gas
1,045 MWIn study Pittsburg, OKSPP Mar 2025target 2031
Gas project ERAS-2025-004, Oklahoma County
Gas
763 MWIn study Oklahoma, OKSPP Sep 2025target 2030
Gas project ERAS-2025-026, Comanche County
Gas
744 MWIn study Comanche, OKSPP Oct 2025target 2029
Gas project GEN-2024-299, Oklahoma County
Gas
744 MWIn study Oklahoma, OKSPP Mar 2025target 2032
Gas project ERAS-2025-024, Comanche County
Gas
744 MWIn study Comanche, OKSPP Oct 2025target 2029
Gas project GEN-2024-128, Caddo County
Gas
690 MWIn study Caddo, OKSPP Mar 2025target 2030
Onshore wind project GEN-2024-345, Nowata County
Onshore wind
600 MWIn study Nowata, OKSPP Mar 2025target 2030
Onshore wind project GEN-2016-119, Kingfisher County
Onshore wind
600 MWAgreement signed Kingfisher, OKSPP Nov 20162025
Gas project GEN-2024-GR5, Chouteau County
Gas
594 MWAgreement signed Chouteau, OKSPP Aug 2024target 2026
Gas project ERAS-2025-023, Rogers County
Gas
510 MWIn study Rogers, OKSPP Oct 2025target 2029
Solar + storage project GEN-2024-165, Coal County
Solar + storage
500 MWIn study Coal, OKSPP Mar 2025target 2030
Solar + storage project GEN-2024-294, Mayes County
Solar + storage
500 MWIn study Mayes, OKSPP Mar 2025target 2030
Solar project GEN-2020-087, Comanche County
Solar
500 MWIn study Comanche, OKSPP Apr 2020target 2026
Gas project ERAS-2025-010, Oklahoma County
Gas
496 MWIn study Oklahoma, OKSPP Sep 2025target 2029
Gas project GEN-2024-013, Mcclain County
Gas
496 MWIn study Mcclain, OKSPP Aug 2024target 2030
Gas project GEN-2024-321, Seminole County
Gas
493 MWIn study Seminole, OKSPP Mar 2025target 2030
Gas project GEN-2024-GR1, Oklahoma County
Gas
492 MWAgreement signed Oklahoma, OKSPP Jan 2024target 2026
Solar + storage project GEN-2023-102, Woods County
Solar + storage
475 MWIn study Woods, OKSPP Oct 2023target 2029
Gas project GEN-2024-247, Payne County
Gas
457 MWIn study Payne, OKSPP Mar 2025target 2030
Coal project ERAS-2025-009, Chouteau County
Coal
450 MWIn study Chouteau, OKSPP Oct 2025target 2026
Other project GEN-2025-SR9, Muskogee County
Other
410 MWIn study Muskogee, OKSPP May 2025target 2029
Solar project GEN-2024-268, Muskogee County
Solar
390 MWIn study Muskogee, OKSPP Mar 2025target 2030
Gas project GEN-2024-323, Choctaw County
Gas
357 MWIn study Choctaw, OKSPP Mar 2025target 2029
Onshore wind project GEN-2016-141, Texas County
Onshore wind
350 MWAgreement signed Texas, OKSPP Nov 2016target 2029
Onshore wind project GEN-2016-142, Texas County
Onshore wind
350 MWAgreement signed Texas, OKSPP Nov 2016target 2029
Solar project GEN-2024-338, Johnston County
Solar
350 MWIn study Johnston, OKSPP Mar 2025target 2030
Onshore wind project GEN-2025-GR1, Grant County
Onshore wind
300 MWIn study Grant, OKSPP Dec 2024target 2027
Solar project GEN-2024-316, Atoka County
Solar
300 MWIn study Atoka, OKSPP Mar 2025target 2030
Solar project GEN-2021-053, Muskogee County
Solar
300 MWAgreement signed Muskogee, OKSPP Apr 2021target 2031
Solar project GEN-2018-048, Caddo County
Solar
300 MWAgreement signed Caddo, OKSPP May 2018target 2028
Gas project GEN-2024-254, Canadian County
Gas
300 MWIn study Canadian, OKSPP Mar 2025target 2027
Solar + storage project GEN-2024-113, Sequoyah County
Solar + storage
300 MWIn study Sequoyah, OKSPP Mar 2025target 2028
Onshore wind project GEN-2024-240, Nowata County
Onshore wind
300 MWIn study Nowata, OKSPP Mar 2025target 2029
Gas project GEN-2024-255, Oklahoma County
Gas
300 MWIn study Oklahoma, OKSPP Mar 2025target 2027
Gas project GEN-2024-252, Canadian County
Gas
300 MWIn study Canadian, OKSPP Mar 2025target 2027
Onshore wind project GEN-2024-GR6, Kay County
Onshore wind
300 MWIn study Kay, OKSPP Jul 2024target 2027
Onshore wind project GEN-2017-137, Oklahoma County
Onshore wind
295 MWAgreement signed Oklahoma, OKSPP Nov 2017target 2030
Solar project GEN-2022-016, Woodward County
Solar
288 MWIn study Woodward, OKSPP Jun 2022target 2028
Battery storage project GEN-2025-SR28, Beaver County
Battery storage
263 MWIn study Beaver, OKSPP Aug 2025target 2027
Onshore wind project GEN-2017-149, Johnston County
Onshore wind
258 MWAgreement signed Johnston, OKSPP Nov 2017target 2027
Solar project GEN-2018-055, Grady County
Solar
252 MWAgreement signed Grady, OKSPP May 2018target 2026
Onshore wind project GEN-2021-016, Johnston County
Onshore wind
250 MWIn study Johnston, OKSPP Apr 2021target 2029
Battery storage project GEN-2024-171, Tulsa County
Battery storage
250 MWIn study Tulsa, OKSPP Mar 2025target 2028
Solar project GEN-2024-083, Choctaw County
Solar
250 MWIn study Choctaw, OKSPP Oct 2024target 2029
Battery storage project GEN-2024-242, Carter County
Battery storage
250 MWIn study Carter, OKSPP Mar 2025target 2029
Solar + storage project GEN-2024-337, Carter County
Solar + storage
250 MWIn study Carter, OKSPP Mar 2025target 2029
Solar project GEN-2017-150, Grady County
Solar
250 MWAgreement signed Grady, OKSPP Nov 2017target 2026
Onshore wind project GEN-2024-291, Pittsburg County
Onshore wind
250 MWIn study Pittsburg, OKSPP Mar 2025target 2030
Page 1 of 5

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)