πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues

OCTARY USA Β· INTERCONNECTION QUEUES

Interconnection queue in PJM (Mid-Atlantic, Midwest) (2023 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown15614.6 GW
Active in queue14.6 GW156 requests
Agreement signed0.0 MW0 requests
Withdrawn11867 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

156 requests Β· page 1 of 4
ProjectCapacityStatusLocationRegionQueuedOnline
Offshore wind project AI2-431, Atlantic County
Offshore wind
2,139 MWIn study Atlantic, NJPJM Mar 2023target 2030
Offshore wind project AJ1-015, Monmouth County
Offshore wind
1,342 MWIn study Monmouth, NJPJM Jun 2023target 2030
Battery storage project AI2-457, Charles County
Battery storage
1,122 MWIn study Charles, MDPJM Mar 2023target 2027
Solar + storage project AJ1-008, Clermont County
Solar + storage
800 MWIn study Clermont, OHPJM May 2023target 2028
Battery storage project AJ1-012, Lake County
Battery storage
354 MWIn study Lake, ILPJM May 2023target 2027
Battery storage project AJ1-011, Lake County
Battery storage
328 MWIn study Lake, ILPJM May 2023target 2027
Solar + storage project AI2-443, Greene County
Solar + storage
300 MWIn study Greene, PAPJM Mar 2023target 2027
Solar project AI2-081, Logan County
Solar
271 MWIn study Logan, OHPJM Feb 2023target 2025
Battery storage project AJ1-014, Will County
Battery storage
260 MWIn study Will, ILPJM May 2023target 2027
Battery storage project AI2-068, Monmouth County
Battery storage
250 MWIn study Monmouth, NJPJM Feb 2023target 2026
Battery storage project AJ1-013, Will County
Battery storage
250 MWIn study Will, ILPJM May 2023target 2027
Battery storage project AI2-069, Monmouth County
Battery storage
250 MWIn study Monmouth, NJPJM Feb 2023target 2026
Battery storage project AI2-045, City Of Virginia Beach County
Battery storage
150 MWIn study City Of Virginia Beach, VAPJM Feb 2023target 2023
Battery storage project AI2-456, King George County
Battery storage
150 MWIn study King George, VAPJM Mar 2023target 2027
Battery storage project AI2-071, Atlantic County
Battery storage
150 MWIn study Atlantic, NJPJM Feb 2023target 2027
Solar + storage project AI2-446, Cambria County
Solar + storage
150 MWIn study Cambria, PAPJM Mar 2023target 2027
Battery storage project AI2-070, Atlantic County
Battery storage
150 MWIn study Atlantic, NJPJM Feb 2023target 2027
Solar project AI2-038, Spotsylvania County
Solar
150 MWIn study Spotsylvania, VAPJM Jan 2023target 2027
Solar project AI2-035, Putnam County
Solar
150 MWIn study Putnam, OHPJM Jan 2023target 2027
Battery storage project AI2-044, City Of Virginia Beach County
Battery storage
150 MWIn study City Of Virginia Beach, VAPJM Feb 2023target 2023
Solar + storage project AI2-445, Tucker County
Solar + storage
148 MWIn study Tucker, WVPJM Mar 2023target 2026
Solar project AI2-037, King And Queen County
Solar
142 MWIn study King And Queen, VAPJM Jan 2023target 2027
Onshore wind project AI2-390, Mclean County
Onshore wind
134 MWIn study Mclean, ILPJM Mar 2023target 2027
Battery storage project AI2-230, Caroline County
Battery storage
120 MWIn study Caroline, VAPJM Mar 2023target 2023
Battery storage project AI2-231, Prince William County
Battery storage
120 MWIn study Prince William, VAPJM Mar 2023target 2023
Battery storage project AI2-114, Augusta County
Battery storage
100 MWIn study Augusta, VAPJM Mar 2023target 2029
Solar project AI2-036, Augusta County
Solar
100 MWIn study Augusta, VAPJM Jan 2023target 2027
Battery storage project AJ1-019, Southampton County
Battery storage
100 MWIn study Southampton, VAPJM Jun 2023target 2028
Battery storage project AJ1-003, Mecklenburg County
Battery storage
100 MWIn study Mecklenburg, VAPJM Apr 2023target 2028
Battery storage project AJ1-002, Rockingham County
Battery storage
100 MWIn study Rockingham, VAPJM Apr 2023target 2028
Battery storage project AJ1-016, Cambria County
Battery storage
100 MWIn study Cambria, PAPJM Jun 2023target 2028
Solar project AI2-328, Madison County
Solar
100 MWIn study Madison, OHPJM Mar 2023target 2026
Battery storage project AI2-039, Surry County
Battery storage
100 MWIn study Surry, VAPJM Feb 2023target 2026
Solar project AI2-329, Madison County
Solar
100 MWIn study Madison, OHPJM Mar 2023target 2026
Onshore wind project AI2-488, Lee County
Onshore wind
97.2 MWIn study Lee, ILPJM Mar 2023target 2026
Onshore wind project AI2-487, Bureau County
Onshore wind
97.2 MWIn study Bureau, ILPJM Mar 2023target 2026
Solar project AJ1-020, Caroline County
Solar
86.4 MWIn study Caroline, VAPJM Jun 2023target 2029
Solar project AI2-115, Delaware County
Solar
84.0 MWIn study Delaware, INPJM Feb 2023target 2026
Solar project AI2-330, Madison County
Solar
83.5 MWIn study Madison, OHPJM Mar 2023target 2028
Solar project AI2-063, Mckean County
Solar
82.5 MWIn study Mckean, PAPJM Feb 2023target 2027
Onshore wind project AI2-167, Logan County
Onshore wind
78.0 MWIn study Logan, ILPJM Mar 2023target 2024
Onshore wind project AI2-216, Pulaski County
Onshore wind
77.0 MWIn study Pulaski, VAPJM Mar 2023target 2028
Battery storage project AI2-040, Orange County
Battery storage
75.0 MWIn study Orange, VAPJM Feb 2023target 2026
Battery storage project AI2-041, Halifax County
Battery storage
75.0 MWIn study Halifax, VAPJM Feb 2023target 2026
Solar project AI2-409, Dekalb County
Solar
72.0 MWIn study Dekalb, ILPJM Mar 2023target 2026
Solar project AI2-164, Wood County
Solar
72.0 MWIn study Wood, OHPJM Mar 2023target 2025
Gas project AJ1-023, Trumbull County
Gas
70.0 MWIn study Trumbull, OHPJM Jun 2023target 2024
Battery storage project AI2-052, Ocean County
Battery storage
70.0 MWIn study Ocean, NJPJM Feb 2023target 2027
Solar project AI2-358, Van Buren County
Solar
70.0 MWIn study Van Buren, MIPJM Mar 2023target 2028
Solar project AI2-195, Lycoming County
Solar
69.9 MWIn study Lycoming, PAPJM Mar 2023target 2025
Page 1 of 4

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)