OCTARY USA Β· INTERCONNECTION QUEUES

Interconnection queue in PJM (Mid-Atlantic, Midwest) (2022 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown30137.9 GW
Active in queue37.9 GW301 requests
Agreement signed0.0 MW0 requests
Withdrawn18219.3 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

301 requests Β· page 1 of 7
ProjectCapacityStatusLocationRegionQueuedOnline
Offshore wind project AI1-001, Monmouth County
Offshore wind
2,100 MWIn study Monmouth, NJPJM Apr 2022target 2029
Offshore wind project AI1-109, Middlesex County
Offshore wind
1,310 MWIn study Middlesex, NJPJM Sep 2022target 2029
Offshore wind project AI1-111, Middlesex County
Offshore wind
1,310 MWIn study Middlesex, NJPJM Sep 2022target 2029
Offshore wind project AI1-110, Monmouth County
Offshore wind
1,310 MWIn study Monmouth, NJPJM Sep 2022target 2029
Solar project AH2-351
Solar
1,000 MWIn study KYPJM Mar 2022target 2027
Solar project AH2-353
Solar
1,000 MWIn study KYPJM Mar 2022target 2028
Solar project AH2-348, Daviess County
Solar
700 MWIn study Daviess, INPJM Mar 2022target 2025
Battery storage project AH2-416, Livingston County
Battery storage
450 MWIn study Livingston, ILPJM Mar 2022target 2026
Battery storage project AI1-022, Huntington County
Battery storage
450 MWIn study Huntington, INPJM Apr 2022target 2026
Battery storage project AH2-333, Salem County
Battery storage
415 MWIn study Salem, NJPJM Mar 2022target 2025
Solar project AH2-352
Solar
400 MWIn study INPJM Mar 2022target 2026
Solar project AH2-257, Vermillion County
Solar
400 MWIn study Vermillion, INPJM Mar 2022target 2024
Solar + storage project AH2-413, Huntington County
Solar + storage
365 MWIn study Huntington, INPJM Mar 2022target 2026
Solar project AH2-340, Stark County
Solar
350 MWIn study Stark, ILPJM Mar 2022target 2027
Battery storage project AH2-414, Huntington County
Battery storage
350 MWIn study Huntington, INPJM Mar 2022target 2026
Battery storage project AH2-133, City Of Chesapeake County
Battery storage
300 MWIn study City Of Chesapeake, VAPJM Mar 2022target 2027
Onshore wind project AH2-270, Whiteside County
Onshore wind
300 MWIn study Whiteside, ILPJM Mar 2022target 2026
Solar project AI1-203, Lunenburg County
Solar
300 MWIn study Lunenburg, VAPJM Sep 2022target 2027
Battery storage project AI1-024, Mclean County
Battery storage
300 MWIn study Mclean, ILPJM Apr 2022target 2026
Battery storage project AI1-017, Surry County
Battery storage
300 MWIn study Surry, VAPJM Apr 2022target 2026
Battery storage project AH2-334, Camden County
Battery storage
300 MWIn study Camden, NJPJM Mar 2022target 2025
Battery storage project AH2-415, Livingston County
Battery storage
300 MWIn study Livingston, ILPJM Mar 2022target 2026
Battery storage project AI1-018, Spotsylvania County
Battery storage
300 MWIn study Spotsylvania, VAPJM Apr 2022target 2026
Solar project AI1-085, Wayne County
Solar
290 MWIn study Wayne, INPJM Jul 2022target 2030
Solar project AH2-322, Pittsylvania County
Solar
290 MWIn study Pittsylvania, VAPJM Mar 2022target 2025
Battery storage project AI1-187, Hunterdon County
Battery storage
280 MWIn study Hunterdon, NJPJM Sep 2022target 2027
Solar project AH2-342, Stark County
Solar
280 MWIn study Stark, ILPJM Mar 2022target 2027
Solar project AI1-040, Elk County
Solar
250 MWIn study Elk, PAPJM Apr 2022target 2025
Solar + storage project AH2-112, St. Joseph County
Solar + storage
250 MWIn study St. Joseph, INPJM Feb 2022target 2026
Battery storage project AI1-149, Mchenry County
Battery storage
250 MWIn study Mchenry, ILPJM Sep 2022target 2025
Solar + storage project AI1-172, Grundy County
Solar + storage
250 MWIn study Grundy, ILPJM Sep 2022target 2028
Battery storage project AI1-167, Clermont County
Battery storage
250 MWIn study Clermont, OHPJM Sep 2022target 2028
Solar project AH2-069, Wythe County
Solar
250 MWIn study Wythe, VAPJM Jan 2022target 2025
Solar + storage project AH2-113, Livingston County
Solar + storage
250 MWIn study Livingston, ILPJM Feb 2022target 2026
Battery storage project AI1-154, Will County
Battery storage
230 MWIn study Will, ILPJM Sep 2022target 2027
Battery storage project AH2-421, Grundy County
Battery storage
230 MWIn study Grundy, ILPJM Mar 2022target 2025
Battery storage project AI1-185, Augusta County
Battery storage
210 MWIn study Augusta, VAPJM Sep 2022target 2027
Solar + storage project AH2-419, Laporte County
Solar + storage
210 MWIn study Laporte, INPJM Mar 2022target 2026
Solar project AH2-397, Somerset County
Solar
200 MWIn study Somerset, PAPJM Mar 2022target 2026
Solar + storage project AI1-039, Clearfield County
Solar + storage
200 MWIn study Clearfield, PAPJM Apr 2022target 2025
Solar + storage project AI1-134, Grant County
Solar + storage
200 MWIn study Grant, INPJM Sep 2022target 2029
Battery storage project AH2-102, Franklin County
Battery storage
200 MWIn study Franklin, VAPJM Jan 2022target 2026
Battery storage project AH2-378A, Gloucester County
Battery storage
200 MWIn study Gloucester, NJPJM Mar 2022target 2025
Solar + storage project AH2-363, Kankakee County
Solar + storage
200 MWIn study Kankakee, ILPJM Mar 2022target 2027
Battery storage project AH2-265, Charles County
Battery storage
200 MWIn study Charles, MDPJM Mar 2022target 2026
Solar project AI1-103, Champaign County
Solar
200 MWIn study Champaign, OHPJM Aug 2022target 2029
Battery storage project AI1-013, Charles City County
Battery storage
200 MWIn study Charles City, VAPJM Apr 2022target 2026
Battery storage project AH2-103, Fayette County
Battery storage
200 MWIn study Fayette, PAPJM Feb 2022target 2026
Onshore wind project AI1-168, Coshocton County
Onshore wind
200 MWIn study Coshocton, OHPJM Sep 2022target 2027
Onshore wind project AI1-191, Stephenson County
Onshore wind
200 MWIn study Stephenson, ILPJM Sep 2022target 2027
Page 1 of 7

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)